(8/12/2011) Keith Marvin - Bethel: Sod Quantity ResponsePage 1
From:
"Dean Dumke" <deand@JRJPaving.com>
To:
"Keith Marvin" <kmarvin@coppelltx.gov>
CC:
"Caleb Thornhill" <bct@freese.com>, "Marty Murphy" <Martym@JRJPaving.com>
Date:
1/6/2011 7:51 PM
Subject:
Bethel: Sod Quantity Response
Attachments:
RFI 024 Site Sod and Curlex Installation.xlsx
Keith & Caleb,
Please see attached RFI 024 regard the Site Sod and Curlex installation
on this project. There seems to be a discrepancy with what was
calculated on the initial plan "estimate of the necessary quantity"
versus what is actually used on the project.
JRJ is in the process of getting verification for the areas in which the
sod and curlex were installed. Once these measurements have been
received, a copy of the areas will be given to the COCoppell for payment
for sod and curlex installed on this project.
The project has 1845 linear feet of construction area, not including the
intersection area.
For example, if 1845 is taken and 10 foot of sod was installed on each
side of roadway, the calculation comes to 4100 square yards, which blows
the initial estimate of 2225 square yards out of the water.
There are very few areas on this project in which sod or curlex was
installed that was due to going outside job limits. I can assure you
that with Larry Davis on site, me, the HOA Presidents and their
respected subdivisions, Luis Parjes and Phil Berkebile, we did not go
over our limits and if we did the area was minimal. JRJ and their
subcontractors, along with the COCoppell and Freese & Nichols have
provided a great looking product/job that we have all been complimented
on by the Bethel Rd residents.
As we always have done, JRJ will work on quantifying these areas and
will get with you to go over once we do. Until we do so, I will only
submit the bid quantity.
Thank you,
Dean Dumke
Sr Project Manager
#469-223-7879
JRJ PAVING, L. P.
_______________________
-----Original Message-----
From: Keith Marvin [mailto:kmarvin@coppelltx.gov]
Sent: Thursday, January 06, 2011 8:09 AM
To: Dean Dumke
Cc: Caleb Thornhill
Subject: Sod Quantity
(8/12/2011) Keith Marvin - Bethel: Sod Quantity ResponsePage 2
Dean,
I received your voice mail about sod quantity. Sod is one of those
items that is specifically listed as a "Plans Quantity Item". Plans
quantity items are paid at the amount listed in the bid schedule. This
is essentially a lump sum item where the engineer has given you his
estimate of the necessary quantity.
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
JRJ PAVING, L. P.
_______________________
1805 Royal Lane, Suite 107
Dallas, Texas 75229
214-466-8340 Phone
214-466-8354 Fax
REQUEST FOR INFORMATION
Project:Bethel Road
RFI No:24
Date:January 6, 2011
Subject:Project Sod
Reference Drawing:All Sheets
INFORMATION REQUESTED:
1.I have received Keith's email regarding the sod on this project and with all of the changes
that were made on this project, JRJ feels that Freese & Nichols needs to relook at their
"estimate of the necessary quantity" for this project.
There have been trees that had to be removed, storm drain pipe, and additional items
changed on this project that were not listed on the initial drawings.
JRJ is requesting how his "estimate of the necessary quantity" was obtained and calculated.
JRJ is in the process of quantifying the areas in which sod and curlex/seed locations were
installed on this project.
Requested by:
Dean Dumke
Sr Project Manager
deand@jrjpaving.com
Mobile: 469-223-7879