Loading...
ST0301A-CS110110 (3) (8/12/2011) Keith Marvin - RE: Bethel Road - Bridge Erosion ProtectionPage 1 From: Keith Marvin To:Dumke, Dean CC:Murphy, Marty Date: 1/10/2011 12:13 PM Subject: RE: Bethel Road - Bridge Erosion Protection Attachments:CHGORD 4.pdf Dean, Attached is a draft the proposed change order number 4. I have included everything I know to be outstanding. Please review and let me know if I'm missing anything. I have a few comments on the exclusions shown in your proposal: 1. Exclusions 3 and 4 - We expect JRJ to be the "others" that ARK referrers to. The city will not provide traffic control, barricading, erosion control, etc. Restoration in the form of curlex, seed, or other suitable material will be required. 2. Exclusion 5 - This work will be included in the 2-year maintenance period where JRJ warrants against defects in materials or workmanship. We will not hold you responsible for failure under extreme flood conditions. Let me know if any of these are an issue. Also give me an indication of when they can start and how long it will take. Thanks, Keith Keith Marvin, P.E. Project Engineer (972) 304-3681 >>> "Dean Dumke" <deand@JRJPaving.com> 1/10/2011 8:54 AM >>> Keith, Attached is the change order associated with Option 2: Gabion Toe Wall & 12 Inch Gabion Mattress. Please review change order and if this is correct, please respond informing me to proceed with this, per change order 21R. This work is subsidiary to the contract work time which JRJ has asked to have stopped yesterday, 01/07/11. Thank you, Dean Dumke Sr Project Manager #469-223-7879 JRJ PAVING, L. P. (8/12/2011) Keith Marvin - RE: Bethel Road - Bridge Erosion ProtectionPage 2 _______________________ -----Original Message----- From: Keith Marvin [mailto:kmarvin@coppelltx.gov] Sent: Friday, January 07, 2011 3:00 PM To: Dean Dumke Cc: Marty Murphy Subject: Re: Bethel Road - Bridge Erosion Protection Dean, Please provide me with a change order proposal for the work including the gabion mattress. I will place this work on one final change order with any additional outstanding changes including the reduction for the guardrail and the traffic signal controller cabinet. Keith Keith Marvin, P.E. Project Engineer (972) 304-3681 >>> "Dean Dumke" <deand@JRJPaving.com> 1/6/2011 6:30 PM >>> Keith, Attached is the revised quotes and sketch of area in which I received from Ark Construction for the repair at the NE corner of the bridge. The change order includes 2 options. Please review and let me know which one you choose and I will then send you a revised change order with the one you pick, plus 10% as we have previously discussed. If you need to speak to me regarding this, please feel free to contact me. Thank you, Dean Dumke Sr Project Manager #469-223-7879 JRJ PAVING, L. P. (8/12/2011) Keith Marvin - RE: Bethel Road - Bridge Erosion ProtectionPage 3 _______________________