Keith Marvin - RE: The Reserve Electrical Issue
From: "Dean Dumke" <deand@JRJPaving.com>
To:"Joseph M. Altadonna" <joemaltadonna@yahoo.com>, "Clay"
<Clay@outdoorsignature.com>, <kmarvin@ci.coppell.tx.us>
Date: 1/20/2011 11:49 AM
Subject: RE: The Reserve Electrical Issue
Joe,
I will be there at 10am and will have my electrician attend also for his opinion.
Dean Dumke
Sr Project Manager
#469-223-7879
JRJ PAVING, L. P.
_______________________
From: Joseph M. Altadonna [mailto:joemaltadonna@yahoo.com]
Sent: Wednesday, January 19, 2011 5:07 PM
To: Clay; Dean Dumke; kmarvin@ci.coppell.tx.us
Subject: The Reserve Electrical Issue
a good suggestion has been brought forward to assemble (all of us if possible) and
directly assess what is missing or needed from the project at The Reserve. I would
like to propose Monday the 24th after 10AM. It's important to have subject matter
experts on electrical to really make this a meaningful and hopefully brief session. If
this day does not work, please propose another time and day.
I am out of town till Sunday evening.
thank you for your patience in this matter!
Joe Altadonna
972-742-0040 cell
joemaltadonna@yahoo.com
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4D38212DCity_...8/12/2011
Page 1 of 1
Keith Marvin - The Reserve-please read/Action requested
From: "Joseph M. Altadonna" <joemaltadonna@yahoo.com>
To: <kmarvin@ci.coppell.tx.us>
Date: 1/19/2011 3:58 PM
Subject: The Reserve-please read/Action requested
CC: Tom Fee <tfee@feesmith.com>
Keith,
Hope you are well and holidays were satisfying. The Bethel Road project is looking
very good and I am pleased with the final product and vision for the next phase. I
have proceeded with our new entry project as foretold but have come to a complete
stop as the island does not have power. This was not the case prior to JRJ
construction.
I have reached out to JRJ Paving and was told that they have no additional
responsibility to our association and we are basically on our own. I can't imagine why
they do not feel accountable to this restoration. I have approved of their work on
landscaping and sprinkler replacement (Dean Dumke has the letter in hand).
Our entire community has been respectful of the various crews that have been
parking and working on our streets for half of 2010, and now we are told the
electrical that was functioning prior to JRJs work is our problem to solve.
I would appreciate your urgent attention to this matter.
Joe Altadonna
972-742-0040 cell
joemaltadonna@yahoo.com