(8/29/2011) Keith Marvin - ST 99-02 West Sandy Lake RoadPage 1
From: Keith Marvin
To:bryan.williams@oncor.com
CC:Seely, Chris B.
Date: 6/2/2011 5:00 PM
Subject: ST 99-02 West Sandy Lake Road
Attachments:ST99-02B Ph 2 P&P.pdf
Bryan,
Thanks for calling me back this morning to discuss our upcoming W. Sandy Lake Road project. I'm attaching a PDF file with
the plan and profile of our current plans.
We have a conflict with Oncor's transmission lines at the east end of the project. There are poles along the South side of
Sandy Lake at approximate stations 109+60, and 107+00 that are in direct conflict with the roadway, and will need to be
relocated.
There are conflicts with the sidewalk at stations 103+00 and 90+50. I will discuss these two locations with the engineer
and see if we can reroute the sidewalk to avoid the conflict on our end.
There is an additional phase of this project that will come shortly after this one that will require the relocation of additional
poles west of this project. We are still working on detailed plans for this future section, but it might be beneficial to try to
do all the relocations as one project.
Our goal is to be prepared to begin construction on this project around the first of the year.
Thanks for your assistance. Please let me know if I can provide any additional information.
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681