Keith Marvin - Re: Southwestern Blvd.
From:Ken Griffin
To:Ben Chessar
Date:3/19/2009 5:51 PM
Subject:Re: Southwestern Blvd.
CC:Dave Littleton; Keith Marvin
Ben
Sorry for the delay. Currently, most utilities are relocated or in the process, except for a school fiber
optic on TXU poles. We are working with the school vendor to obtain a timeline. Revised plans are in
and both sections are at 95% complete. I've spent my time trying to go through the AIA documents
and match them up with COG standards to try to eliminate any conflicting information and ensure that
the final product meets our standards.
Keith is out for Spring Break this week, but I'll have him contact you next week to provide a more
detailed status of the plans. Sometimes, 95% plans have addressed all issues and the submitting
engineer is waiting on the City to agree before they call them 100%.
Keith's update will also provide the latest on the utility relocates that I may not be aware of.
Ken Griffin, P. E.
Director of Engineering & Public Works
972-304-3680
kgriffin@ci.coppell.tx.us
>>> "Ben Chessar" <BenC@PacTrust.com> 3/18/2009 7:55 PM >>>
Ken,
It has been some time since we spoke last. I left more than two messages with Rhonda in your office as well as
sent you emails.
I would like to think that no news is good news, however, a return phone call or some type of a response from
the City of Coppell would be greatly appreciated.
Regards,
J. Benjamin Chessar