ST0701-CS090902:■: 1201 North Bowser Rd. Halff A ichardson, Texas 75081 Inc. • ( 214) 346 -6200 ENGINEERS ARCHITECTS SCIENTISTS PLANNERS SURVEYORS Fax (214) 739 -0095 FIELD OBSERVATION '1' 1 AVO: 24732 & 25816 Date /time: August 31, 2009 3:00 PM Project Description: Southwestern Boulevard Improvements Contractor /Subcontractor: Lacy Construction Engineer's Representative: Jorge L. Rodriguez, P.E. WEATHER AND SITE CONDITIONS: Hot and Sunny EQUIPMENT ON JOBSITE: Earth moving equipment Excavation equipment STORED MATERIALS: Dirt, gravel WORK IN PROGRESS: Earthwork, traffic control, erosion control LABOR FORCE ON JOBSITE: N/A DIRECTIONS GIVEN TO CONTRACTOR OR OTHER CONVERSATIONS WITH CONTRACTOR: None COMMENTS: At the time of the visit clearing and grubbing were under construction. Silt fence was installed to the north side of the road from the bridge to Belt Line Road. A few gravel and dirt stockpiles were poured in the site. Traffic control is insufficient and shall be improved. Check dams shall be installed in the creek per plans as soon as possible. A big hole is open and no protection around it. Shall be protected immediately. See pictures. COPIES: ❑ OWNER ❑ ARCHITECT ❑ CONTRACTOR ❑ ❑ FILE Page 1 of 1 Keith Marvin - Field report no.l From: "Rodriguez, Jorge" <jrodriguezghalff.com> To: "Keith Marvin" <kmarvingci.coppell.tx.us >, "Matt Oyen" <Matt0gPacTrust.com> Date: 9/2/2009 9:05 AM Subject: Field report no. l CC: "Littleton, Dave" <dlittletonghalff.com> Attachments: rptl - 8- 31- 09.doc; 2009 -09 -01 001 Jpg; 2009 -09 -01 003.jpg; 2009 -09 -01 01 0.jpg; 2009- 09-01 012.jpg; 2009 -09 -01 013.jpg; 2009 -09 -01 020.jpg; 2009 -09 -01 021.jpg; 2009 -09- 01 024.jpg; 2009 -09 -01 026.jpg; 2009 -09 -01 027.jpg; 2009 -09 -01 028.jpg Hi guys I attach field report no. 1 and several pictures for your records. Below is a briefly photo explanation. Picture 001. This traffic control was installed for Coppell Road improvements. No traffic control signs have been installed for Southwestern Blvd. Picture 003. Clearing and grubbing along the south side of Southwestern Blvd. Stockpiles between Coppell Rd and the Bridge. Channelizing devices along Southwestern Blvd. Picture 010. Clearing and grubbing and stockpiles nearest to the creek. Picture 012. Silt fence to the north of Southwestern Blvd. Picture 013. Hole without fence protection. Picture 020. Trailer and equipments Picture 021. Earthwork at creel location Picture 024. Earthwork to the south of Southwestern Blvd.between the Bridge and Belt Line Picture 026. Earthwork in front of the school. Picture 027. Earthwork at Howell Drive. Picture 028. Silt fence to the north side of Southwestern Blvd and Howell Drive If any question please call me, Thanks Jorge Rodriguez, P.E. INEZ Project Manager Ign HALFF HALFF ASSOCIATES, INC. 1201 N. Bowser Road Richardson, Texas 75081 Phone 214 - 346 -6203 Fax 214 - 739 -0095 www.halff.com file: / /C: \Documents and Settings \radloo \Local Settings\ Temp \XPgrpwise \4A9E3559City_... 8/30/2011 rte:. yr p e d'nE nos_ !r. Wr Rr n '.: -W. .r ,� o ! ,F 9 i ����� i �� : �'.�.. mimc i a R , s w •. PI — u a 16 4 ilaft H r" v . . _� _ m _ - _ - . tie i . ,'., - � • ® - � . .. s•+� F. SIR r. r a IL x .a • 26 — ... „..r • �� . �' � — ., � � � x — ... or 11116 . ..A " •, _ � 3 1 ��• s •� .a' RT .a � wm mw _ v moll, r VA milisaill 4 06 ! mg u rw -� - �� z.. Icy• - di • x � �p a .. . ,�' m ., Ail �: � � � � � , : ■ � z \ L I W - �