Keith Marvin - Southwestern Boulevard - Overall Schedule
From: "Matt Oyen" <MattO@PacTrust.com>
To:"Harris, Kody" <kharris@lhlacy.com>, "Keith Marvin"
<KMARVIN@ci.coppell.tx.us>, "Richard Odell" <RODELL@ci.coppell.tx.us>, "Ken
Griffin" <KGRIFFIN@ci.coppell.tx.us>, "Littleton, Dave" <dlittleton@halff.com>,
<jrodriguez@halff.com>
Date: 9/23/2009 11:42 AM
Subject: Southwestern Boulevard - Overall Schedule
Attachments: Southwestern Schedule 9-11-09.pdf
Attached please find a PDF copy of Lacy's overall schedule per our discussion.
Thanks,
Matt
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4ABA098CCity...8/30/2011
IDTask NameWorkAug 16, '09Aug 23, '09Aug 30, '09Sep 6, '09Sep 13, '09Sep 20, '09Sep 27, '09Oct 4, '09Oct 11, '09Oct 18, '09Oct 25, '09Nov 1, '09Nov 8, '09Nov 15, '09Nov 22, '09Nov 29,
'09Dec 6, '09Dec 13, '09Dec 20, '09Dec 27, '09Jan 3, '10Jan 10, '10Jan 17, '10Jan 24, '10Jan 31, '10Feb 7, '10Feb 14, '10Feb 21, '10Feb 28, '10Mar 7, '10Mar 14, '10Mar 21, '10
FSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSS
MTWTFSSMTWTFSSMTWTFSSMTWTFS
1Notice to proceed0 days
100%
2Erosion Control0 days
100%
3Barricades0 days
100%
4Clearing and Grubbing0 days
100%
5Strip Top Soil and Stock Pile0 days
100%
6Sanitary Sewer 15+13-38+000 days
0%
7Sanitary Sewer Line C 15+13-38+000 days
0%
8Sanitary Sewer Line B 15+13-38+000 days
0%
9Storm Pipe Line A 0+00-15+130 days
100%
10Storm Pipe Line A 15+13-38+000 days
0%
11Storm Line B Station 25+50-33+500 days
0%
12Strom Lateral A-1, A-2 Partial0 days
0%
13Storm Lateral B-13, B-12, B-11, B-10, B-90 days
0%
14Storm Lateral B-8, B-7, B-60 days
0%
15Storm Lateral B-5, B-3, B-10 days
0%
16Storm Lateral A-1, A-2, A-3, A-4, A-50 days
0%
17Inlet Bottoms Southside 0+00-38+000 days
20%
18Water Line A 15+13-38+000 days
0%
198" Water Line Station 26+71-15+13-38+000 days
0%
20Water Line "F" Patrial 15+13-38+000 days
0%
21Water Line "H" Partial 15+13-38+000 days
0%
226" Water 20+98 Partial 15+13-38+000 days
0%
23Water Line A 01+00-15+130 days
100%
24Install All Service and Water Leads Partial 01+00-38+000 days
0%
25Excavation and Grade0 days
0%
26Lime Southsied 01+00-38+000 days
0%
27Detour0 days
0%
28Trim Lime0 days
0%
29Concrete Paving Southside 01+00-38+000 days
0%
30Inlet Tops Southside 01+00-38+000 days
0%
31Backfill Southside 01+00-38+000 days
0%
32Block Wall0 days
0%
33Striping and Signs Southside 01+00-38+000 days
0%
34Southside Electrical Conduit 01+00-38+000 days
0%
35Hydro Mulch Soutside 01+00-38+000 days
0%
36Clean Up Southside 01+00-38+000 days
0%
37Traffic Switch Southside 01+00-38+000 days
0%
38Demo Existing Aspalt Road Northside 01+00-38+000 days
0%
39Clearing Grubbing Northside 01+00-38+000 days
0%
40Sanitary Sewer Line B Northside 01+00-15+130 days
0%
41Sanitary Sewer Line E North side 15+13-38+000 days
0%
42Storm Lateral A-1 01+00-15+130 days
0%
43Storm Lateral B-1, B-2, B-3, B-4, B-6, B-8, B-10, B-120 days
0%
44Storm Lateral A-1, A-3, A-50 days
0%
45Complete All Water Service and Leads Northside 01+00-38+000 days
0%
46Inlet Bottoms0 days
0%
47Excavation and Grading0 days
0%
48Northside Lime 01+00-38+000 days
0%
49Northside Concrete Paving 01+00-38+000 days
0%
50Inlet Tops Northside 01+00-38+000 days
0%
51Northside Driveways Pavement Leave Outs Phase 1 01+00-38+000 days
0%
52Back fill0 days
0%
53Striping and Signs0 days
0%
54Sidewalk0 days
0%
55Hydro Mulch 0 days
0%
56
57
58Mobilization0 days
0%
59Survey Benchmarks0 days
0%
60Locate Exst. Lines0 days
0%
61Bridge Layout0 days
0%
62Drilled Shafts0 days
0%
63Abutments0 days
0%
64Bents0 days
0%
65Concn. Riprap0 days
0%
66Rock RipRap0 days
0%
67Slab Beams0 days
0%
68Bridge Slab0 days
0%
69Approach Slabs0 days
0%
70Conc Surf Treat0 days
0%
71Rail TY T4110 days
0%
72Temp conc Rail0 days
0%
73Sot and TL2 Trans0 days
0%
74Temp Crash Cush 0 days
0%
75Paint T411 Rail 0 days
0%
76Demo Old Bridge0 days
0%
77Excavation0 days
0%
78DrLD Shaft Layout0 days
0%
79Drilled Shafts0 days
0%
80Abutments0 days
0%
81Concrete Rip Rap0 days
0%
82Bents0 days
0%
83Slab Beams0 days
0%
84Stl Plate @ Slab0 days
0%
85Bridge Slab0 days
0%
86Bridge Sidewalk0 days
0%
87Rail TY C4110 days
0%
88Approach Slabs0 days
0%
89Apr Slb Sdwlks0 days
0%
90Conc. Surf Trtmt0 days
0%
91Opaque Sealer0 days
0%
92Single Crsh Cush0 days
0%
93Remove Temp Rail0 days
0%
94Clean & Sell0 days
0%
Project: Southwestern Blvd. # 5262
TaskSplitProgressMilestoneSummaryProject SummaryExternal TasksExternal MilestoneDeadline
Date: Wed 9/23/09
Page 1