FIELD OBSERVATION REPORT NO. 4
AVO: 24732 & 25816 Date/time: November 12, 2009
10:00 A.M.
Project Description: Southwestern Boulevard Improvements
Contractor/Subcontractor: Lacy Construction
Engineer's Representative: Jonathan McCulley
WEATHER AND SITE CONDITIONS:
Cool, Sunny, Dry
EQUIPMENT ON JOBSITE:
Backhoe
STORED MATERIALS:
Rebar cage for Abutment 4. Formwork. Miscellaneous rebar.
WORK IN PROGRESS:
Forming for Abutment 4. Columns for Bent 2.
LABOR FORCE ON JOBSITE:
Three workers on bridge site; one operating equipment.
DIRECTIONS GIVEN TO CONTRACTOR OR OTHER CONVERSATIONS WITH CONTRACTOR:
Discussed RFI #5, 6, and 7.
COMMENTS:
Abutment 1 was poured (no backwall yet). All drilled shafts were in place. Bent 2 columns were under
construction. Drilled shaft rebar extending above shaft on Bent 3 requires straightening. Abutment 4 rebar
cage was ready and forming for the abutment was in place. The contractor is hoping to start placing beams in
a couple of weeks.
COPIES: OWNER ARCHITECT CONTRACTOR FILE