FIELD OBSERVATION REPORT NO. 5
AVO: 24732 & 25816 Date/time: November 13, 2009
10:00 AM
Project Description: Southwestern Boulevard Improvements
Contractor/Subcontractor: Lacy Construction
Engineer's Representative: Robert Gossett, E.I.T.
WEATHER AND SITE CONDITIONS:
Overcast
EQUIPMENT ON JOBSITE:
Earth moving equipments
Excavation equipments
STORED MATERIALS:
Dirt, gravel, storm drain, waste water and water pipes
WORK IN PROGRESS:
Storm drainage, and bridge construction
LABOR FORCE ON JOBSITE:
Equipment operators and laborers.
DIRECTIONS GIVEN TO CONTRACTOR OR OTHER CONVERSATIONS WITH CONTRACTOR:
Checked in and explained what I was doing.
COMMENTS:
At the time of the visit the bridge abutments and the drainage were under construction. Storm lines from
Coppell Rd. to Grapevine Creek seem to be in place. The majority of line A, east of the creek seems to be
installed. No signs of line B were visible. The water and waste water mains seemed to mostly complete on
both sides of the creek. The temporary road west of the creek has been constructed and in use. There has
been no road pavement or earthwork done at this time.
COPIES: OWNER ARCHITECT CONTRACTOR FILE