ST0701-CS100107Pagel of 3 Keith Marvin - RE: ww stub outs From: "Matt Oyen" <Matt0gPacTrust.com> To: "Farris, Kody" <kharrisglhlacy.com >, "Littleton, Dave" <dlittletonghalff.com> Date: 1/7/2010 6:11 PM Subject: RE: ww stub outs CC: "Keith Marvin" <kmarvin @ci.coppell.tx.us >, "Rodriguez, Jorge" <jodriguez @halff.com >, "Long, Clint" <clong @lhlacy.com >, "Murawski, Ron" <rmurawski @lhlacy.com >, "Selby, Mark" <mselbyglhlacy.com> Please proceed with pot holing each side on a T &M basis. Please also provide us with the pricing information tomorrow for crossing #1 and #3, so that we have the information to make decisions on placement of any potential laterals before next week. Thanks, Matt From: Harris, Kody [mailto: kharris @lhlacy.com] Sent: Thursday, January 07, 2010 1:11 PM To: Littleton, Dave; Matt Oyen Cc: Keith Marvin; Rodriguez, Jorge; Long, Clint; Murawski, Ron; Selby, Mark Subject: RE: ww stub outs Dave, On location # 1 we will not be able to expose the 24" water where it shown to be pot holed. This location is in the center of the temporary detour that is currently under traffic. With that said we can pot hole the 24" water east and west of the detour and project an elevation based on that information. Please let me know if this is how you would like us to proceed. This work will take place first thing in the morning. Thanks, KODYHARRIS PROJECT MA NA CER LEI TA CY COMPANY From: Littleton, Dave [mailto:dlittleton @halff.com] Sent: Thursday, January 07, 2010 11:59 AM To: Matt Oyen; Harris, Kody Cc: Keith Marvin; Rodriguez, Jorge Subject: RE: ww stub outs Matt and Kod the lateral material will be C900 Pipe (Cl 150). Crossin of the 24-inch and 12-inch pipe will b(; concrete encased (+/- 30 LF) somehow centerin a section of pipe on the crossin We'll put to a profile once we g et the elevation of the 24-inch pipe (top elevation and measured OD of the water main) file: / /C: \Documents and Settings \radloo \Local Settings\ Temp \XPgrpwise \4B4623E9City_... 8/31/2011 Page 2 of 3 From: Matt Oyen [ma iIto: Matto @PacTrust.com] Sent: Thursday, January 07, 2010 11:00 AM To: Harris, Kody Cc: Keith Marvin; Littleton, Dave; Rodriguez, Jorge Subject: RE: ww stub outs Kody - Given the status of your pavement layout can you please provide us with an estimate for completing the crossings at location #1 and #3. Our desire would be to construct both of these locations to provide future flexibility based on our conversations with Halff. However, given your status with the pavement I would like to know what the cost implications are associated with constructing crossing #1. 1 know Halff was also working with the City to see what would be required to approve these crossings, so that we can see what the true timing implications are. I was also wondering what the status of the field verification at the crossings with the existing water lines is. Please give me a call when you have a moment to discuss. Thanks, Matt From: Rodriguez, Jorge [mailto:jrodriguez @halff.com] Sent: Thursday, January 07, 2010 7:42 AM To: Matt Oyen; Harris, Kody Cc: Keith Marvin; Littleton, Dave Subject: ww stub outs Hi guys I visited the site yesterday afternoon and the rebar in the crossing area of stub out # 1 are in place. As I mentioned on my yesterday email, I strongly recommend an stub out in this area, so the rebar in place is in conflict with the stub out. Please call Dave or me to discuss how to proceed. Please see the attached pictures. Thanks Jorge Rodriguez, P.E. P HALFF roject Manager MEN HALFF ASSOCIATES, INC. 1201 N. Bowser Road Richardson, Texas 75081 Phone 214 - 346 -6203 Fax 214 - 739 -0095 www.halff.com Privileged /Confidential Information may be contained in this message. If you are not the addressee indicated in this message, have received this file: / /C: \Documents and Settings \radloo \Local Settings\ Temp \XPgrpwise \4B4623E9City_... 8/31/2011 1 • 1 i k O g! _ 16 .�. ��� O man , T � -. MIN MIKE.-� FLA -1 F.� _ � �ae a - • 111. `r Y ai H IM — low 1 ,Im EP W -km AmI=� Nj� J = 'IML d ty —EPA mp- N. Mr. Alm,- iM -0 I JX- 1 3PAMP�.� 4 �, am Wil Now - .-' P-C I nl�