(9/7/2011) Keith Marvin - RE: Final As-Built Drawings and Close Out documentsPage 1
From: Keith Marvin
To:Odell, Richard; Rodriguez, Jorge
CC:Harris, Kody; Oyen, Matt
Date: 8/10/2010 9:34 AM
Subject: RE: Final As-Built Drawings and Close Out documents
Jorge,
Please submit one set of black line prints for review prior to final submittal of as-builts.
I have not heard back on the scheduling of the TDLR inspection. Have you requested the inspection yet?
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> "Rodriguez, Jorge" <jrodriguez@halff.com> 8/10/2010 9:31 AM >>>
Rick
I have plan to submit the AS BUILT drawings to the City this week. I followed the construction sets with the mark-ups that
Kody Harris gave to me. He told me that you went with him making your mark-ups on this sets. Please let me know if you
request to review prior to submitting final ones to the City.
Thanks
Jorge
-----Original Message-----
From: Keith Marvin [mailto:kmarvin@coppelltx.gov]
Sent: Tuesday, July 06, 2010 4:56 PM
To: Rodriguez, Jorge; Kody Harris
Cc: Richard Odell; Matt Oyen
Subject: RE: Final As-Built Drawings and Close Out documents
Please coordinate your as-built work with Rick O'Dell. He'll need to review and sign off on preliminary as-builts prior to
submitting final ones to the city. Final submittal will be one set of mylars, one set of black line drawings, and a CD with
CADD files for both projects.
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> "Rodriguez, Jorge" <jrodriguez@halff.com> 7/6/2010 4:45 PM >>>
Kody
Could you please provide the final as-built mark-ups. I am able to start working on the preparation of the as-built drawings
as soon as you provide the requested mark-ups.
Thanks
Jorge
From: Matt Oyen [mailto:MattO@PacTrust.com]
(9/7/2011) Keith Marvin - RE: Final As-Built Drawings and Close Out documentsPage 2
Sent: Wednesday, June 30, 2010 10:23 AM
To: Rodriguez, Jorge; Harris, Kody; Littleton, Dave
Subject: Final As-Built Drawings and Close Out documents
I wanted to see if you have begun coordination on final as-builts and close out documents. I am assuming that we are
close enough to complete at this point that we could begin preparation of the as-built drawings. Obviously we would like to
close out this project with the City as quickly as possible and would ask that you coordinate on the as-built effort if you
have not already done so.
Thanks,
Matthew Oyen, PE
Construction Manager
Pacific Realty Associates, L.P. (PacTrust)
15350 SW Sequoia Pkwy, Suite 300
Portland, OR 97224
Office: 503 624-6300
Cell: 503 523-7619
matto@pactrust.com