(9/13/2011) Keith Marvin - Re: Bethel/Coppell RoadPage 1
From: Keith Marvin
To:Phillips, Clay
CC:Griffin, Ken
Date: 1/2/2008 4:04 PM
Subject: Re: Bethel/Coppell Road
I spoke with Richard Brewster today from Oncor. He will work on a cost estimate for burying these lines. I expect it will
take 3 weeks before we see an estimate.
Keith
>>> Clay Phillips 12/21/2007 6:08 PM >>>
Thanks........just let us know what you find out.
-----Original Message-----
From: Keith Marvin
Cc: Clay Phillips <CPHILLIP@ci.coppell.tx.us>
To: Ken Griffin <KGRIFFIN@ci.coppell.tx.us>
Sent: 12/21/2007 10:51:10 AM
Subject: Bethel/Coppell Road
Ken & Clay,
Richard Brewster with Oncor Electric is out through January 2nd. I talked with Jerry Bates and he said he didn't have
anyone other than Richard that could work up the cost to burry the overhead lines in the Old Town area.
I left a message with Richard and I will touch base with him again after the new year.
Keith