ST0702-CS090626 (2)(9/13/2011) Keith Marvin - coppell road south deduct Page - 1 ]
From: "James Scott" <Jamess @JRJPaving.com>
To: "Keith Marvin" <kmarvin @ci.coppell.tx.us>
Date: 6/26/2009 5:02 PM
Subject: coppell road south deduct
Attachments: nevillcopier @jrjpaving com_20090626_163948.pdf
Ketih,
I attached the deduct here
Thank you
James Scott
J RJ Paving
214- 466 -8430
- - - -- Original Message---- -
From: Keith Marvin [ mailto :kmarvin @ci.coppell.tx.us]
Sent: Friday, June 19, 2009 5:27 PM
To: James Scott
Subject: Kimbel Kourt
James,
I discussed the request for information relative to the Kimbel Kourt bid
with our Purchasing Manager. He has advised me not to release the CAD
files. It looks like you will need to do a take off from the sections
included in the plans.
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304 -3681
JRJ
214- 466 -8340 PAVING, LP P.O. Box 59934
FAX (Sales) 214 -466 -8354
FAX (Admin) 214 - 466 -8352
City of Coppell
Att: Keith Marvin, P.E.
Project Engineer
Coppell Road South Paving and Drainage Improvements
Mr. Marvin,
1805 Royal Lane, Suite 107
Dallas, TX 75229
This letter is to inform you that if the above mentioned street can be closed down in either 1
or 2 sections then their will be a deduct from item 2 traffic control.
If the north section, from approximately 5 +95 — 14 +10, is closed then the deduct for the north section
will be $22,914.00
If the south section, from approximately 15 +00 — 20 +30, is closed then the deduct for the south
section will be $18,126.00
If both the north and south sections are closed then the total deduct will be $41,040.00