(9/14/2011) Keith Marvin - RE: CHANGE ORDER 1 FOR COPPELL ROADPage 1
From: Keith Marvin
To:Scott, James
CC:Martym@JRJPaving.com; Odell, Richard
Date: 8/26/2009 10:35 AM
Subject: RE: CHANGE ORDER 1 FOR COPPELL ROAD
James,
We are in agreement with the work as proposed. I will add this item to the Change order #1. Once I have the price for
the 16" water box I will send CO#1 over to you.
Please proceed with the adjustment to this sewer service.
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> "James Scott" <Jamess@JRJPaving.com> 8/26/2009 9:36 AM >>>
After taling with my utilitie sub, it appears that they ran into s
problem with the SS at the service center. They need to lower it to
connect it. The attached change order reflects the work that neds to be
done. Apperently this is holding up my sub right now.
Thank you
-----Original Message-----
From: Keith Marvin [mailto:kmarvin@ci.coppell.tx.us]
Sent: Wednesday, August 26, 2009 8:47 AM
To: James Scott
Cc: Richard Odell; Marty Murphy
Subject: Re: CHANGE ORDER 1 FOR COPPELL ROAD
James,
Any word on the 16" water line box?
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> "James Scott" <Jamess@JRJPaving.com> 8/24/2009 10:26 AM >>>
Keith,
This is the change order # 1 we will send over the pricing for the 16"
box etc... by tomorrow
This is everything else tho.
(9/14/2011) Keith Marvin - RE: CHANGE ORDER 1 FOR COPPELL ROADPage 2
James Scott