ST0702-CN090809
CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
PROJECT: South Coppell Road (ST 07-02)
CONTRACTOR: JRJ Paving
OWNER: City of Coppell
CHANGE ORDER NO.: Two (2) DATE: September 8, 2009
Item Description Quantity Unit Unit Price Total
ADD: 1 Connect to Existing 1 EA 1980.00 $1,980.00
Sanitary Sewer
2 8” PVC SDR-35 484 LF 42.90 $20,763.60
3 Trench Safety 484 LF 25.75 $12,463.00
4 Remove Existing 2 EA 990.00 $1,980.00
Manhole
5 4’ Manhole 4 EA 2530.00 $10,120.00
6 Extra Depth 8.00 VF 132.00 $1,056.00
Manhole
7 4” Service 5.00 EA 742.50 $3,712.50
8 Testing Sewer Line 484 LF 2.75 $1,237.50
9 Test Manhole 5.00 EA 247.50 $1,237.50
Total Revision to Contract Amount $54,550.10
Previous contract amount $1,340,724.19
Net increase in contract amount $54,550.10
Revised contract amount $1,395,274.29
Net increase in contract time of completion 0
Revised Contract time of completion 210 Calendar Days
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full
accord and satisfaction of all past and future liability originating under any clause in the Contract by
reason of this revision to the Contract.
________________________________________
Recommended by City Engineer Date
________________________________________
Agreed to by Contractor Date
________________________________________
Accepted by City Date