(9/20/2011) Keith Marvin - RE: COPPELL ROAD SOUTHPage 1
From:
"Marty Murphy" <Martym@JRJPaving.com>
To:
"Keith Marvin" <kmarvin@ci.coppell.tx.us>
Date:
1/11/2010 3:43 PM
Subject:
RE: COPPELL ROAD SOUTH
I don't have James' proposal to you in front of me so I am not sure hat
he gave you. Jimmy met with Rick and then gave us the measurements and I
fairly certain it did not include the driveway, as you said it is
covered under another pay item and uses different material.
I will put it where ever you want but I have to buy 24 tons at a minimum
and I will furnish and install it for $50.00ton.
-----Original Message-----
From: Keith Marvin [mailto:kmarvin@ci.coppell.tx.us]
Sent: Monday, January 11, 2010 3:23 PM
To: Marty Murphy
Subject: Re: COPPELL ROAD SOUTH
Marty,
I'm having a hard time justifying the expense. I think we should do
something from the top of the headwall to the edge of the slope of the
yard. I do not think we should bring it into the yard, and especially
not all the way to the asphalt. The driveway itself is covered under
pay item # 129. My estimate is it would take about 9 tons to cover this
area.
The proposed cost of $100/ton seems high to me.
If we can cover the area described above for $500 then I would authorize
you to proceed.
Call me in the office to discuss this.
Thanks,
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> "Marty Murphy" <Martym@JRJPaving.com> 1/11/2010 2:12 PM >>>
Any news on the rip rap at the end of Mitchell, I have a crew that can
install this week if we get the approval.
Marty Murphy,
Business Manager
JRJ Paving, L.P.
1805 Royal Lane, Ste. 107
Dallas, TX. 75229
214-466-8340
214-466-8354 fax