ST0702-CS100407
(9/29/2011) Keith Marvin - RE: Coppell RoadPage 1
From:
"Marty Murphy" <Martym@JRJPaving.com>
To:
"Keith Marvin" <kmarvin@coppelltx.gov>
Date:
4/7/2010 12:46 PM
Subject:
RE: Coppell Road
I am going to proceed with the sod and hydromulch along the street. If
you are confident that the change order will be approved then I will
also proceed with the remaining work as the 27th allows us time to still
bill this work in April.
-----Original Message-----
From: Keith Marvin [mailto:kmarvin@coppelltx.gov]
Sent: Wednesday, April 07, 2010 9:16 AM
To: Marty Murphy
Cc: Richard Odell
Subject: Re: Coppell Road
Marty,
I'm going to have to go to City Council for approval of the change order
for the channel since it will exceed $25,000. ($24,951.50 + $12,827.10)
My next opportunity for Council action is April 27th.
That having been said, there is no reason to not put the sod down since
we have a contract price for that. Your proposed price for the sod plus
hydromulch behind the sidewalk is within $700 of the contract price for
sod. Like I said on the phone the other day, if you want to get both of
these items done, and are willing to accept the contract amount of
$10,879.00 than we can move forward with both of those. We would then
only be adding the "offsite" work to the change order.
I'll work up the change order and plan to take it to City Council on
4/27.
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> "Marty Murphy" <Martym@JRJPaving.com> 4/7/2010 8:57 AM >>>
Any idea when we will be released on the change order for the grass? My
guys are chomping at the bit to get finished.
Marty Murphy,
Business Manager
JRJ Paving, L.P.
1805 Royal Lane, Ste. 107
Dallas, TX. 75229
214-466-8340
214-466-8354 fax