From: "Wes McClure" <Wes.McClure @txdot.gov>
To: "Ken Griffin" <KGRIFFIN @ci.coppell.tx.us>
Date: 1/27/2011 9:14 AM
Subject: Fwd: CSJ 0918 -45 -773 - Sandy Lake costs
Good Morning Ken,
City's estimated costs to cancel Sandy Lake Rd project are provided below. I do not anticipate any
additional charges at this time but Kelly's caveat should be noted. I will close our system to further
charges at this time.
If the City decides to cancel the project please provide a letter of termination per our discussion.
Please contact me with any questions.
Wes
Wesley G. McClure, P.E.
Dallas District Programming Engineer
TxDOT Dallas District
Wes.McClure@TxDOT.gov
(214) 320 -4461
»> Kelly Davis 1/27/2011 8:42 AM »>
Wes,
The subject CSJ is still active in FIMS. So, the figures I am going to give you do not include any salaries
not yet posted.
As of 1/26/2011:
Total Spent to Date: $101,157.71
LG Amt on Deposit: 9,594.24
Amount Due from LG: $ 91,563.47
David Smith will need to be notified to inactivate this CSJ in FIMS. Also, I will need a letter or e-mail from
the LG stating they wish to cancel this project.
Let me know if you need anything else.
Thanks.
Note - Effective August 1, 2010, I have a new e-mail address:
Kelly.Davis @txdot.gov. Please update this information in your address book.
Thank you.
Kelly D. Davis
TxDOT - Dallas Dist (18)
Project Delivery Section
PO Box 133067
Dallas, TX 75313 -3067
(214)320 -4424