(10/11/2011) Keith Marvin - TWC COST FOR BETHEL RD PROJECTPage 1
From:
"Cheney, David" <david.cheney@twcable.com>
To:
Keith Marvin <KMARVIN@coppelltx.gov>
Date:
8/2/2011 11:22 AM
Subject:
TWC COST FOR BETHEL RD PROJECT
Attachments:
TWC Bethel Rd Estiamate (doing ascity Rd Improvement vs Beautification Proj
ect).xlsx
Keith,
You will see my notes on this estimate. Any questions give me a call. I really couldn't throw anything in
here to speak to schedules as this would take allot less time for us to do once the new poles were placed.
Good luck with City Council. Please let me know as soon as you can which option you want us to go with.
thanks
________________________________
This E-mail and any of its attachments may contain Time Warner Cable proprietary information, which is
privileged, confidential, or subject to copyright belonging to Time Warner Cable. This E-mail is intended
solely for the use of the individual or entity to which it is addressed. If you are not the intended recipient of
this E-mail, you are hereby notified that any dissemination, distribution, copying, or action taken in relation
to the contents of and attachments to this E-mail is strictly prohibited and may be unlawful. If you have
received this E-mail in error, please notify the sender immediately and permanently delete the original and
any copy of this E-mail and any printout.
TWC Contract Labor Estimate
City Of Coppell
CLIENT:
PROJECT SUPERVISOR
PROJECT MANAGER:
PROJECT NUMBER ID:
Bethel Rd Relo
PROJECT NAME:
CategoryWork CodeDescriptionUnitAmountCostTOTAL
A12OH024Pole Transfers (Maintenance) Straight thruEach$56.00$840.00
15
A02 Total$840.00
A15OH086Overlash Composite Coax - NEW BUILD ONLYFT1643$0.90$1,478.70
A15OH088Wreck Out Aerial Plant BIDFT1643$0.19$312.17
A05 Total$1,790.87
U15UG065Materials (see attached BOM tab)Each1$1,153.00$1,153.00
U15UG066In-House LaborHrs40$56.00$2,240.00
U05 Total$3,393.00
Grand Total$6,023.87
THIS IS AN ESTIMATE OF WHAT THE BETEHEL RD PROJECT WOULD COST TWC -NOT KNOWING EXACTLY WHERE ONCOR WILL PLACE THEIR NEW POLES
FOR THE RD PROJECT PORTION ONLY
THIS IS ASSUMING TWC WILL BE ABLE TO TRANSFER ALL FIBER TO NEW POLES WITHOUT HAVING TO
REBUILD OR CUT ANY FIBER.
TWC WOULD HAVE TO REBUILD OUR COAX
THIS DOES NOT INCLUDE BURYING ANY EXISTING CROSSINGS- ALL REMAINS AERIAL ON THIS ESTIMATE
THE PREVIOUS REVISED ESTIMATE INCLUDED BURYING ALL TWC LINES FROM FREEPORT TO JUST
EAST OF SOUTH COPPELL RD.