ST8505-CS 890825GINN, INC.
CONSULTING ENGINEERS
August 25, 1989
Mr. Frank Trando
City of Coppell
P.O. Box 478
Coppell, TX 75019
Re-
Belt Line Road
Final Application for Payment
Dear Mr. Trando:
Enclosed are 4 copies of the Final Payment Request (No. 26) for
the above referenced project.
Our office has reviewed this request and concur that the final
contract amount is $5,650,587.94 as shown.
It is our recommendation that $250,000 of retainage be released
at this time and that the City hold $55,604.13 until the Final
Punch List items are corrected and the City accepts the project.
Enclosed also are the Final Close-Out Documents which include
Consent of Surety, Waiver of Lien certifying that all labor and
materials are paid for, and various correspondence. Under
separate cover we are transmitting final sets of record drawings
to the Department of Public Works.
We will advise your office when the project is ready for
acceptance and when to release the final retainage.
Sincerely,
H. Wayne Gihn, P.E.
CC:
Alan D. Ratliff
Russell Doyle, P.E.
Steve Goram
File 255