ST8505-CS 890814GINN, INC. August 14, 1989 FILE COPY Mr. Alan D. Ratliff, City Manager City of Coppell P.O. Box 478 Coppell, TX 75019 Re: Status Report - Belt Line Road South Dear Mr. Ratliff: We have been meeting with Ed Bell Construction Co. during the past week to finalize the quantities and costs for the Belt Line Road project. LANDSCAPE During this past week the Contractor has re-hydromulched some of the bare spots. He has also been issued a final punch list of items to correct before final acceptance of the proj. ect. RETAINAGE As soon as we receive the Final Request for Payment from the Contractor, we will review it and recommend to the City that the retainage (currently approximately $300,000) be reduced to an amount applicable to cover only the remaining deficiencies. TIMETABLE FOR ACCEPTANCE The current plan is to allow a couple of weeks for the new hydro mulch to "take hold" and then apply a week k~ller (spray application) around the first of September. Prior to that time any weed killer might harm the immature hydromulch grass. We will coordinate with the Parks Department for the assumption of maintenance duties once the weeds are killed and the punch list completed. Please call if you have any questions. sincerely, H. Wayne Ginn, P.E. cc: FORWARDED TO ~u-,,ll Doyle, P.~.. MAYOR AAq),COUNCIL File 255 DATE: ~//)/? 9 . 17103 Preston Road · Suite 1~ · LB 118 · Dall~, Tex~ 75248 · Phone 214/248-4~