Keith Marvin - Old Town Coppell - portion of Bethel Road Phase II
From: Caleb Thornhill <bct@freese.com>
To: Keith Marvin <kmarvin@coppelltx.gov>
Date: 11/8/2010 3:57 PM
Subject: Old Town Coppell - portion of Bethel Road Phase II
CC: CPL03243 <CPL03243@freese.com>, CPL09446 <CPL09446@freese.com>, TriciaHa...
Keith,
Below is a breakdown of the costs to add portions of Bethel Road Phase II to the Old Town Coppell project.
Bethel Road Phase II Limits: Bethel Road from Freeport to Coppell Road/ Main Street; Coppell Road from Bethel
Road to Cooper Street
Survey Cost: $10,000
Design Cost: $53,000
Construction Cost: $2,400,000
Construction Cost - Bethel Road from Coppell Road/ Main Street to Coppell Road South: $350,000
Take a look and let me know if you need additional information.
B. Caleb Thornhill P.E.
Project Manager
Freese and Nichols, Inc.
Main: 214-217-2200
Direct: 214-217-2282
Fax: 214-920-2565
Email: bct@freese.com
Please consider the environment before printing this message.
This electronic mail message is intended exclusively for the individual or entity to which it is addressed. This message, together with any attachment,
may contain the sender's organization's confidential and privileged information. The recipient is hereby notified to treat the information as confidential
and privileged and to not disclose or use the information except as authorized by sender's organization. Any unauthorized review, printing, retention,
copying, disclosure, distribution, retransmission, dissemination or other use of, or taking of any action in reliance upon, this information by persons or
entities other than the intended recipient is prohibited. If you received this message in error, please immediately contact the sender by reply email and
delete all copies of the material from any computer. Thank you for your cooperation.
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4CD81DD9Cit...10/14/2011