Keith Marvin - RE: Old Town Coppell - Landscape Meeting
From: Tricia Hatley <thh@freese.com>
To: Caleb Thornhill <bct@freese.com>, Keith Marvin <kmarvin@coppelltx.gov>, ...
Date: 3/9/2011 10:39 AM
Subject: RE: Old Town Coppell - Landscape Meeting
CC: CPL09446 <CPL09446@freese.com>
Keith – couple of questions for you as a follow up to the meeting:
I understand that you want us to add construction plans for the water and sewer lines in the alleys
serving the townhomes. Do you want us to also include the alley paving and storm drain work?
For the retail buildings on the west side of the site, we had planned on providing water and sewer from
the loop road in the back. Sounded like you wanted us to provide water and sewer from the front off of
Main Street during your discussions last week. Do we need to make this change? Most retail buildings
have restrooms in the back so I wanted to make sure that the developer is on board with that change
before we starting redoing things.
Explain a little more about phasing of the landscape plans. You want us to design all of the landscaping
that we originally scoped out but you want it in two packages? One to go in with the roadway
construction and another to go after the restaurants and pavilion are complete? Need to clarify this as
it will create some extra work to separate them, not from a design standpoint but as far as the
construction documents are concerned. I’m assuming that phasing would also include the street lighting
and irrigation.
Here is a draft schedule based on our previous discussions. Please let me know if you have any issues with these
milestones and this process for getting the plans wrapped up:
th
Draft landscape plan email submittal (approx 60% plans) – March 24
th
Receive city comments – March 30
th
90% plan submittal – April 12
rd
Receive city comments – no later than May 3
th
100% plans, specs, & bid quantities – May 24
Advertise – early to mid June
th
Award construction contract – August 9
Trish
Tricia H. Hatley, P.E., LEED AP
Principal, East Transportation/Infrastructure
From: Caleb Thornhill
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4D7758C5City...10/17/2011
Page 2 of 2
Sent: Wednesday, March 09, 2011 7:25 AM
To: Keith Marvin; Mindi Hurley
Cc: CPL09446; Tricia Hatley
Subject: Old Town Coppell - Landscape Meeting
Keith/Mindi,
th
Attached are the meeting minutes from our meeting on Monday, February 28, 2011. Please review and let me
know if you have any comments or have anything else to add.
B. Caleb Thornhill P.E.
Project Manager
Freese and Nichols, Inc.
Main: 214-217-2200
Direct: 214-217-2282
Fax: 214-920-2565
Email: bct@freese.com
www.freese.com
Please consider the environment before printing this message.
This electronic mail message is intended exclusively for the individual or entity to which it is addressed. This message, together with any attachment,
may contain the sender's organization's confidential and privileged information. The recipient is hereby notified to treat the information as confidential
and privileged and to not disclose or use the information except as authorized by sender's organization. Any unauthorized review, printing, retention,
copying, disclosure, distribution, retransmission, dissemination or other use of, or taking of any action in reliance upon, this information by persons or
entities other than the intended recipient is prohibited. If you received this message in error, please immediately contact the sender by reply email and
delete all copies of the material from any computer. Thank you for your cooperation.
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4D7758C5City...10/17/2011
MEETING MINUTES
PROJECT: Old Town Coppell – CPL09466
NAME OF MEETING: Landscape Discussion, Waterline/ Sewer Revisions
RECORDED BY: B. Caleb Thornhill, P.E.
DATE: February 28, 2011
LOCATION: City of Coppell
ATTENDEES: Clay Phillips (Coppell), Charles Cotton (Developer), Greg Yancey
(Developer), Caleb Thornhill (FNI), Dwight Taylor (FNI), Bill Peck (???),
Matt Steer (Coppell), John Elias (Coppell), Gary Sieb (Coppell), Keith
Marvin (Coppell), Mike Garza (Coppell), Ken Griffin (Coppell), Mindi
Hurley (Coppell)
The following reflects our understanding of the items discussed during the subject meeting. If you
do not notify us within five working days, we will assume that you are in agreement with our
understanding.
ITEM DESCRIPTION PRESENTER
City of Coppell passed out a “Streetscaping” sheet for
1.01 recommendations regarding median plantings John
Dwight Taylor proposed submitting a preliminary “sketch” of the
revised landscaping plan. He asked if it would be beneficial to
submit it to the City for review. Keith Marvin asked that it be DT/Keith
1.02 submitted directly to him and he would distribute it accordingly. Marvin
The City asked FNI to show light pole bases on Paving and
1.03 Landscaping sheets. City
Ken Griffin expressed concern about plantings at the “stop
controlled” intersections. It was decided that the intersection of
Main St./Houston would be a three-way stop
1.04 Ken Griffin
Ken asked FNI to meet the sight triangle requirements for the streets
intersecting South Coppell Road and Bethel Road. Landscaping
1.05 should be limited at these locations. Ken Griffin
Tree plantings along South Coppell Road should be limited in order
1.06 not to conflict with overhead power poles. City
There were discussions of speeds within the Old Town area. Dwight
asked about the use of speed bumps in the area. Ken said he felt
due to the configurations, speed shouldn’t be an issue. The City also
didn’t feel the need for any “Speed Limit” signs within the
1.07 development. All
Keith questioned the light pole spacing requirements. South Coppell
Road design was done with light poles spaced at 60’ C-C. It was
agreed that 60’ C-C is similar to the Firewheel Town Center. Old
1.08 Town would keep the spacing as shown. All
1.09 It was decided that no sidewalk banding. All
ITEM DESCRIPTION PRESENTER
Tree Wells – Ground cover will be provided with root barriers on the
1.10 street side. City
Water and sewer service to be provided for all buildings except for
three facing Hammond street. Greg Yancey will provide a site file
showing all building pad locations and what buildings may require
fire lines. Water and Sewer should run down alley parallel to E. Main
Street. Services need to be provided to all buildings. The alley will
not be paved at this time. Buildings along Travis Street may be
served from front or back. FNI to determine best configuration to
serve this buildings.
1.11 All
Greg made the comment they are tweaking the lots of C7-C10 due to
a drainage easement. The current location has not been set.
1.12 Greg Yancey
Greg is planning 32 Townhomes between E. Main and S. Coppell Rd.
He is planning 12 along Travis Street.
1.13 Greg Yancey
John Elias asked that trees planted along Main Street median be
1.14 offset and not in a straight line. John Elias
Bill Peck asked if FNI could send a cadd file showing the current
1.15 roadway configuration and cross walk locations. FNI to provide Bill Peck/ FNI
The City stated the current parking configuration of 60degree angles
1.16 and 9’x18’ dimensions is acceptable. City.
John stated the sheet handed out for landscaping was only
guidelines. He said if FNI had another similar suggestion they would
1.17 look at it. John Elias
There were questions about potential conflicts with w/ww and
storm drain. It appears from 90% area J-2 is shown incorrectly. FNI
1.18 will analyze. City/FNI
Keith asked if the landscaping should be phased due to potential
damage during the construction of the surrounding buildings. It was
agreed that Phase I of the landscaping should be Main Street. The
inner square will be designed, but built at a later date. All irrigation
for the landscaping will be built in Phase I. FNI will discuss further
1.19 with the city how the plans are separated. City/FNI
1.20
ACTION ITEMS
WHAT WHO WHEN STATUS
1.Greg will provide site plan for future Greg
buildings to FNI and City. Yancey 2 weeks On-going
2.FNI will develop new landscaping
plan based on feedback from 90% plan
meeting. FNI submittal On-going
3.FNI to provide Bill Peck site cadd
file. FNI Done.
4.FNI to provide w/ww service to all
buildings except those facing 90%
Hammon. FNI submittal On-going