WA9601B-CN000207 CITY OF COPPELL, TEXAS
Sandy Lake Road Water Line
Wagon Wheel Ranch Elevated Tank to Denton Tap Road
CHANGE ORDER NO. 3
A. INTENT OF CHANGE ORDER
The intent of this change order is to modify the provisions of the contract entered into between the City of
Coppell, Texas and Fox Contractors, Inc., P.O. Box 951, Midlothian, Texas 76065, for construction of the
Sandy Lake Road Water Line - Wagon Wheel Ranch Elevated Tank to Denton Tap Road, dated December 8,
1998.
B. DESCRIPTION OF CHANGE
This change order covers the additional compensation for delays imposed on the Contractor while alternative
alignment and easement issues were being resolved by the City on the Sandy Lake Road Water Line project.
C. EFFECT OF CHANGE ON CONTRACT AMOUNT
This change order will have the following effect on the cost of this project:
No. 'Description Quantity This C.O.. Quantity unit Price of Change
44 Equipment Move-in, Trench Box 0 1 1 L.S. $5,480.54 $5,480.54
Rental
45 One Crew 0 3 3 Days 1,500.00 4,500.00
Total: ] $9,980.54
Original Contract Amotmt $912,243.50
Change Order No. 1 17,500.00
Change Order No. 2 23,500.00
Change Order No. 3 9,980.54
Revised Contract Amount $963,224.04
D. EFFECT OF CHANGE ON CONTRACT TIME
The work required under this change order would not add any calendar days to this project.
Original Contract Time 200 calendar days
Change Order No. 1 0 calendar days
Change Order No. 2 0 calendar days
Change Order No. 3 0 calendar days
Revised Contract Time 200 calendar days
('214100) Page I of 2
E. AGREEMENT
By the signatures below, duly authorized agents of the City of Coppell, Texas and Fox Contractors, Inc., do
hereby agree to append this Change Order No. 3 to the original contract between themselves, dated
December 8, 1998.
City of Coppe!l, Texas Fox Contractors, Inc.
Owner " Contractor
By: By:
Date: ; i~ ~ 1~5)O Date: c9,,~ '?-- e?e''
Attest: Attest: