Loading...
WA9903-AG 991012CITY COUNCIL MEETING: AGENDA RE~.UEST FORM October 12, 1999 ITEM # ITEM CAPTION: Consider approval of awarding a contract to Shimek, Jacobs and Finklea Consulting Engineers to provide professional services assdciated with the design and installation of Pump #4 at Village Parkway Pump Station in an amount not to exceed $34,500; and authorizing the Mayor to sign. suB~rr~D ~Y: K?~ ~.o'R~, ~..~... See attached memo. ~~, ~! ~ BUDGET AMT. $ FINANCIAL COMMENTS: AMT. EST. $ +\-BUD $ DIR. INITIALS: ~ FIN. REVIEW: CITY MANAGER REVIEW: Agenda Request Form - Revised 2/99 Document Name: #10123 I ] i' To: From: Date: RE: MEMORANDUM FROM THE DEPARTMENT OF ENGINEERING Mayor and City Council Kenneth M. Griffin, P.E., Dir. of Engineering/Public Works ~/,/ October 12, 1999 Consider approval of awarding a contract to Shimek, Jacobs and Finklea Consulting Engineers to provide professional services associated with the design and installation of Pump #4 at Village Parkway Pump Station in an amount not to exceed $34,500; and authorizing the Mayor to sign. In a continuing effort to upgrade the City' s water pumping capabilities and to continue to stay within State guidelines as mandated by the Texas Natural Resources Conservation Commission (TNRCC) the City of Copper needs to pursue the installation of the fourth large pump at Village Parkway Pump Station. Currently there are 3 large pumps and 2 smaller pumps at the pump station. The pump station was designed to install a fourth large pump and based on the growth in the City and peak demands, it is time to install it. In addition to that work, several other items will also be addressed at the pump station. One item that has been a concern of staff in the past is that there are no isolation valves on the other three large pumps. In essence, this means that if a problem were to arise with one of the three large pumps that necessitated removing the pump, then the entire pump station would have to be shut down for a period of time. Obviously, this would be devastating during peak water usage in the summer. The isolation valves would allow us to isolate any of the three pumps to perform either maintenance or emergency work. We will also be upgrading the power feed to the station based on review of the current usage and the anticipated usage with the fourth large pump. Because we have a dual feed to the station, there is a need to replace two smaller transformers with two larger transformers. The above work will bring the Village Parkway Pump Station to its capacity in regard to pumping and storage. The City of Copper is also in the process of updating our Water Master Plan to address other pumping and storage needs. In the past few years, Council may recall that we have completed a six million gallon ground storage tank, added two additional pumps, and replaced our Rate of Flow Controller to allow us flow up to 28 million gallons a day, as opposed to the old Rate of Flow Control which could only deliver 13.5 million gallons a day. We have also recently completed the two million gallon elevated storage tank on the west side of Coppell and upgraded our SCADA System. As can be seen by all these projects, there has been a steady progression of upgrades to the water system to keep up with' demand. While the addition of the fourth pump is the next step in the process, by no means is it the final step. The Water Master Plan update, which should be before Council at the October 26, 1999 meeting for approval, will more than likely recommend a second pump station along with additional ground storage at the second pump station. To continue the progress on updating the City's water system, staff recommends approval of the contract with Shimek, Jacobs and Finklea Consulting Engineers in an amount not to exceed $34,500, and authorizing the Mayor to sign. Staff will be available to answer any questions concerning this item at the Council meeting. SHIMEK, JACOBS & FINKLEA, L.L.P. CONSULTING ENGINEERS 8333 Douglas Avenue, #820 Dallas, Texas 75225-5816 Fax (214) 361-0204 Phone (:;14) 361-7900 ROSS L. JACOBS, P.E. RONALD V. CONWAY, P.E. JOHN W. BIRKHOFF, P.E. JOE R. CARTER, P.E. GARY C. HENDRICKS, P.E. I. C. FINFLEA, P.E. PAUL A. CARLINE, P.E. MATT HICKEY, P.E. September 29, 1999 Mr. Kenneth M. Griffin, P.E. City of Coppell Post Office Box 478 Coppell, Texas 75019 Re: Engineering Services Proposal Village Parkway Pump Station Installation of Pump Number 4 and Isolation Valves for Pumps 1, 2 and 3 Dear Mr. Griffin: ~ As we discussed in our meeting dated September 16, 1999, we have evaluated the requirements for the installation of Pump Number 4 at the Village Parkway Pump Station along with the insertion of pump isolation valves on the existing pumps 1 through 3. The anticipated project scope includes: 0 Installation of Pump Number 4 to generally match the flow and head of the existing three pumps. Our records indicate the pump size would be approximately 450 horsepower and deliver 7,000 gpm at 200 feet total dynamic head. At this stage of preliminary evaluation, we have selected a Ingersoll-Dresser (Worthington) model 10LR-18A pump with a 16-inch impeller as the basis for our preliminary cost estimates and capacity calculation. Based on our evaluation of the existing hydraulic model, with all four large pumps running, the Village Parkway Pump Station is expected to deliver in the range of 25 mgd (17,400 gpm) during the maximum hourly demand condition. In the meeting, the City confirmed the desire to utilize a pump control valve of a design other than the cone valves currently in operation at the station. We recommend the City consider utilize a 16-inch tilted disk check valve with a bottom-mounted dashpot in combination with a "soft start" motor control center. This type of pump control produces a relatively low headloss across the valve. We have specified this type of control valve operation for several other Cities with reasonable success. Installation of this new fourth pump will require the replacement of the existing TxU 750 KVA transformers with two new 2,000 KVA transformers. Normally, TxU does not charge for this change over due to anticipated revenue for the expanded service. However, since the service is dual fed to this pump station, we recommend that no less than one of the larger transformers be included in the project budget. We have included both. With the addition of pumps 5 and 6 and the greater flows now anticipated out of the Village Parkway Pump Station, we discussed the replacement of the venturi flow meter station with a transit time meter. This type of meter can accurately monitor a wide range of flows, produces essentially no headloss and is easily maintained. The new meter can be installed in the existing meter vault and be readily connected to Mr. Kenneth M. Griffin, P.E. City of Coppell September 29, 1999 Page Number 2 the existing SCADA System. For budget purposes we recommend the Badger Model 4500 transit time meter with a windowed spool piece to replace the venturi tube. Installation of isolation valves for Pumps 1, 2 and 3. This scope of work includes the re-configuration of the pump discharge piping and the installation of 24-inch butterfly valves between the pump control valve and the discharge header. This work must be carefully coordinated so that the pump station can remain in service and most likely will include the temporary installation of 24-inch diameter blind flanges on the discharge header. Other miscellaneous items of work include Pump Station Piping, insulation, fittings and painting, construction of a new concrete pad for Pump Number 4, construction of new concrete valve supports for Pumps 1-3, and SCADA System modifications to monitor the new flow meter, pump and motor starter. Based on the scope of the project and assumptions outlined above, our opinion of probable conslruction cost for the addition of Pump Number 4 and the isolation valves for Pumps 1-3, exclusive of engineering, material testing and quality control, is in the range of $310,000. We are enclosing our itemized opinion of construction cost for your use and review. ~ We understand time is of the essence on the project. The following project schedule was discussed and is anticipated: Advertise Project: Bid Opening: Council Award: Work Order Issued: Pump Number 4 in Service: Project Complete: Nov. 26hh and Dec. 3'd, 1999 December 3, 1999 January 1 I, 2000 February l, 2000 May 1, 1999 May 31, 1999 After visiting with a pump manufacturer's representative, we have learned the lead time a standard 450 horsepower pump and motor, from purchase order to delivery to the project site, is between 16 to 18 weeks. With the scheduled outlined above, the pump would not be delivered to the project site until the end of May assuming the purchase order matched the work order date. We have discussed this project schedule with our electrical sub-consultant and have reviewed our own workload. With a focused effort, we believe we can have this project 95% complete within 10 working days after notice to proceed is authorized. Assuming that occurs before October 15, 1999, we should be able to advertise this project for bids by the end of October. The schedule could be moved forward even further if the City was able to provide a purchase order to the contractor in advance or of even date with the award date. Our engineering services for this project shall include the following: BASIC SERVICES A. DESIGN PHASE Preparing plans and specifications for the installation of Pump Number 4 and isolation valves for Pumps 1-3 at the Village Parkway Pump Station. If the project schedule dictates, we will prepare a Mr. Kenneth M. Griffin, P.E. City of Coppell September 29, 1999 Page Number 3 separate bid package for the pumps, control valves and major electrical equipment. The design phase services include: · Construction Plan Sheets prepared at a scale of not less than 1"= 20' · Standard Details · Special Details, coordination requirements and construction sequencing · Cover Sheet, Location Map and Sheet Index · Submittals to State Regulatory Agencies, as required · Preparation of required Highway and Utility Permits, as required · Coordination with Utility Companies · Design review meetings · Opinion of Probable Construction Estimate · Preparation of Specifications and Contract Documents · Printing of preliminary l~ans and specifications for review by the City and Utility Companies B. CONSTRUCTION ADMINISTRATION · Assist in Advertising for Bids · Opening, Tabulation and Evaluating Bids received · Consult with Owner as to actions based on Engineering matters · Assist in execution of Contract Documents · Make periodic visits to the job site · Preparing and issuing routine Field Changes with the Owners approval · Preparing and issuing routine Change Orders with the Owners approval · Review of Shop Drawings, Test Reports and other data · Preparation of Monthly and Final Pay Requests · Conduct a Final Inspection with the Owner · Preparation and delivery of one set of record drawings on mylar sepias to the City II. SPF. CIAI. SF. RVICFS · Design Surveys · Printing of f'mal plans and specifications for distribution to prospective bidders and the successful contractor Mr. Kenneth M. Griffin, P.E. City of Coppell September 29, 1999 Page Number 4 For the above described services, we propose to be compensated on the following basis: BASIC SF, RVICES: Compensation for basic services shall be on a lump sum basis of $32,500 in accordance with the schedule below. A. Design Phase: ..................................................................$24,375 B. Bidding Phase ..................................................................$1,625 C. Construction Administration Phase: ..................................$6,500 H. SPECIAl. SERVICES: Compensation for Special Services shall be based on salary cost times 2.30, with expenses at actual invoice cost times I. 10. We suggest you budget approximately $2,000 in the following amounts for the Special Services: A. Design~r~_eys ........................................................$1,200 B. Printing of Final Plans and Specifications $800 Subtotal, Pump Station: $2,000 Payments are to be made on a monthly based on the percent complete of the design or construction phase for the Basic Services, and based on the actual hourly expenditures for the Special Services. If you are in agreement with this proposal, please have one copy executed on behalf of the City of Coppell and returned to our office. We again look forward to working with you and the City of Coppell on this important project and stand ready to begin work upon your authorization to proceed. Gary C./~dricks APPROVE F TI-IE~ CITY OF COPPELL / SHIMEK, JACOBS & FINKLEA, L.L.P. CONSULTING ENGINEERS Project No. Client: Project: City of Coppell Village Parkway Pump Station Additions Installation of Pump Number 4 and Isolation Valves on 1, 2 and 3 Date: By: ENGINEER'S OPINION OF CONSTRUCTION COST Item No. I Description ] Quantity [ Unit ] Price Brief Project Description: ] [ I Installation of Pump Number 4 to operate at 7,000 gpm at 200 TDH (450HP Ingersoll-Dresser 10LR- 18A) along with Tilted Disc Pump Control Valve and Soft Start Motor Control Center. Project includes the installation of 24-inch butterfly valves on the discharge side of Pumps 1, 2 and 3. Furnish 450 HP Pump and Motor: 7,000 gpm @ 200 Ft TDH (Ingersoll-Dresser 10LR-18A) 1 L.S. Installation of Pump Number 4 and Motor Fumish and Install 16" Tilted Disk Pump Control Valve with Bottom Mounted Dash-pot 9/29/99 3 Pump Number 4 - 4160v Motor Control Center and Soft Start Replace existing TXU 750 KVA Transformer with 2000 KVA 4 Transformer Remove existing Venturi Flow Tube and Transmitter and Replace with Badger 4500 Transit Time Flow Meter with Windowed Spool 5 Piece Furnish and Install 24" butterfly Isolation Valves on Discharge 6 Header of existing Pumps 7 Pump Number 4 - 30" Suction Side Isolation Valve 8 Pump Number 4 - 24" Discharge Side Isolation Valve 9 30" pump suction piping 10 24" pump discharge piping 11 Bends, Fittings, Reducers and Couplings 12 30-inch suction side pipe insulation 13 Pipe and Equipment Painting 14 SCADA System Modifications Contingencies and Miscellaneous Items Subtotal: 1 3 1 1 20 10 1 l 1 1 10% GCH Total: Amount $ 45,000.00 $ 45,000.00 l L.S. $ 25,000.00 $ 25,000.00 I Ea. $ 16,000.00 $ 16,000.00 1 L.S. $ 50,000.00 $ 50,000.00 2 Ea. $ 33,000.00 $ 66,000.00 $ 17,500.00 $ 17,500,00 $ 10,000.00 $ 30,000.00 $ 7,500.00 $ 7,500.00 $ 6,500.00 $ 6,500.00 $ 175.00 $ 3,500.00 $ 150.00 $ 1,500.00 $ 7,500.00 $ 7,500.00 $ 1,500.00 $ 1,500.00 $ 1,500.00 $ 1,500.00 $ 3,000.00 $ 3,000.00 $ 282,000.00 $ 28,200.00 $ 310,200.00 USE: $ 310,000.00 L.S. Ea. Ea. Ea. L.F. L.F. L.S. L.S. L.S. L.S. Page 1 of I '* ' *' I H