Loading...
SS9301-CS 940124KENKO January 24, 1994 Ginn & Case, Inc. 17103 Preston Road Suite 205, LB 118 Dallas, TX 75248 Attn: Mr. Wayne Ginn, P.E. Re: Grapevine Creek Sewer Trunk Main - Branch I & II CoDpell, TX Kenko Job #9306 * Contract time extension Dear Sirs: As discussed in the meeting of January 13, 1994, regarding the referenced project, Kenko requests a contract time extension of 90 calendar days for Change Order No. 3 on behalf of Southland Contracting (ref: Southland's letter of January 21, attached) Kenko, Inc., completed open cut operations up to approximately Station 82+50 on July 28, 1993. It is anticipated that if open cut construction had been utilized through Station 89+13 this work could have been completed by August 14, 1993. However, to minimize damage to existing trees the Owner elected to micro-tunnel this section. This work was performed by Southland Contracting during the months of September, October and November. According to our records this additional micro-tunneling was completed on November 11, 1993. , Please call if you have any questions. Sincerely, Kenko, Inc. cc: Mr. Garreth Campbell, City of Coppell 50UTHWESTERN DIVISION - 164 ! S Addison Rd., Ste. 308 - Dallas, TX 75248 - (2 ! 4) 931-9494 - Fax (214) 931-5474 WESTERN DIVISION - Post Office Box 831 - Calimesa, California 92320 - (909) 795-2568 - Fax (909) 795-1840 CORPORATE OFFICE - ! 694 9 ! st Avenue - Blaine, Minnesota 55449 - (6 ! 2) 786-6510 - Fax (612) 786-6602 SOUTHLAND CONTRACTING 81 .~955298 P.02 ?609?-069? January 21, ~99& ~x [t~,?] ~-~gZ Dan Frettinger Kenko Inc. :: 16415 Addison Road~ Suite 308 Dallas, Texas 75248 Re: Grapevine Creek Sewer Trunk Main, Coppell. Texas Dear Dan: Per your letter dated January 3. 1994. and the discussion at the meeting with Nr. Oinn and Hr. Campbell in Coppell, th~ final decision that, at this time, in order to complete the proiect on time, to not do the ~est side o~ Denton Tap Road with open cut. In order to complete the project in ample time, plus the additional mlcrotunneling which was added, knowing the production was much lower than originally anticipated, we request for that change, an _. additional ninety days to the contract time. We find that the boring .lOg does not accurately indicate what we have found at the Cul De Sac, The roll control reouirement on the ~aehine i:s different in the wet sand and silt than that used in the shale. There£ore the recelvlns shafts ~ill have to be excavated prior to starting a push so that we will have a better fe.~l for how to ~et up. This will continue until we Eot into the solid shale that was anticipated uv the lin~. Sincerely,