Re: Grapevine Creek Sewer Trunk Main -- Branch I & II
Coppell, TX
Kenko Job #9306
* Punch list
Dear Sir:
Kenko, Inc., respectfully request a punch list on the
referenced project for the area from Station 0+00 to Station 68+30.
Kenko has spent the last 2 1/2 weeks completing the line
installation, manholes, testing and televising. At this time Kenko
is waiting for approval from the City to make the tie-ins at
Stations 37+54, 44+65 and 48+66. Before final grading can be
completed in this area all other work items, punch list items, etc.
must be completed. As this area is "politically sensitive" your
assistance in expediting this request is greatly appreciated.
Please call if you have any questions.
Sincerely,
Kenko, Inc.
cc: Mr. Ken Griffin, City of Coppell
Mr. Garreth Campbell
SOUTHWESTERN DIVISION - 16415 Addison Rd., Ste. 308 - Dallas, TX 75248 - (214) 93 i-9494 - Fax (214) 931-5474
WESTERN DIVISION - Posl Office Box 831 - Calimesa, California 92320 - (7 ! 4) 795-2568 - Fax (714) 795- ! 840
CORPORATE OFFICE - 1694 91 st Avenue - Blaine, Minnesota 55449 - (612) 786-6510 - Fax (6 ! 2) 786-6602