ST8807-CS 870529Dallas /Fort Worth
International Airport
Oris W. Dunham, Jr.
Executive Director
May 29, 1987
Mr. Steve Martin
City of Coppell
P.O. Box #78
Coppell, Texas 72019
Dear Mr. Martin:
Enclosed is Tenant Construction Application No. 87-139 for the improvement of
Royal Lane north to Bethel Road, as described in the submitted plans and
specifications and the amendments thereto.
This application is approved subject to the following:
1. All standards of the Dallas-Fort Worth Airport Design Criteria
Manual shall be met.
2. All standards of the Dallas-Fort Worth Airport Building Codes
and Fire Codes shall be met.
3. Submittal of a copy of the contractor's insurance certificate and
payment and performance bonds.
4. Submittal of a complete set of as-built mylars upon completion
of the project. _ ~
The contractor is required to contact ,..ichard McDonald {574-2181 or A1
Magazzine (574-8128) prior to start of wot~q...~ ....... ~
Please note that this work may not commence until you have posted this fully
executed and approved application in a visible location at the job site.
Very.~?ly yours,
Senior Director of
Planning and Engineering
AWM/tlh
enclosure
cc: F. Renfro, C. Fauroat, T. Shehan, B. Swan, D. Showers, C. Williams,
R. McDonald, A. Magazzine, DeShazo, Starek & Tang, Inc.
THE:87-139
Administrative Offices-East Airfield Drive (214) 574-6720 P.O. Drawer DFW, Dallas / Fort Worth Airport, Texas 75261
Application%. 8q- I"'~?
DALLAS/FORT WORTH INTERNATIONAL AIRPORT BOARD
P. O. Drawer DFW
Dallas/Fort Worth Airport, Texas 75261
TENANT CONSTRUCTION OR GRAPHICS APPLICATION
A. INFORMATION FROM APPLICANT (to be completed by Applicant):*
Leaseholder: DFW Airport Telephone No.:
Company Name of Tenant: City of Coppell Telephone No.:
Tenant Contact: Steve Morton (462-0022)
574-8190
462-0022
Description of Work: Paving and drainage improvements on Royal Lane, from I.H. 635 to
Bethel Road. Includes a 16-inch water line and security fence relocation.
Architect/Engineer: DeShazo, Starek & Tang, Inc. Telephone No.: 748-6740
Project Cost: $1,550,084.53
Contractor: Uvalde Construction Company Telephone No.: 631-1750
Proiect Superintendent John Owens Telephone No.: 631-1750
Contractor Address: 2645 Irving Blvd., Dallas, T×~
Signature of Leaseholder Authorized Representative: ~__
Typed Name of Representative: George T. Bonna
*Enclose insurance certificates, bonds, and contracts as outlined on the reverse side of this form.
*If any of these areas are not completed, the Application will not be approved.
B. VERIFICATION OF CONTRACTUAL REQUIREMENTS:
Insurance: I'~ff¢~-~ ¥'~
Contract Administration:
Cost Systems Administration:
Funding Verification:
Bonds:
Lease No.
Contract:
Date:
Date:
Date:
C. APPLICATION IS APPROVED SUBJECT TO THE FOLLOWING CONDITIONS:
Reviewed By: ~ ~#Z~/,8~P'
D"~ering ¢~/~
Date:
Applicant must read the terms and conditions printed on the reverse hereof.
TERMS AND CONDITIONS
The Applicant shall not commence performance of any of the said work prior to posting
a fully executed and approved copy of this application in a visible location convenient to
the site of work. If construction has not commenced within ninety (90) days of the applica-
tion approval date, then this permit is void arid Leaseholder must re-submit a new applica-
tion for approval.
The Applicant shall comply also witi~ such Federal, State, and Municipal taws, statutes,
orders, and regulations, if any, as may be legally applicable to the work or the perfor-
mance thereof, or its employees therein.
The Applicant shall submit the Application and valid insurance certifcates for all projects.
Aisc included for construction projects over $25,000 must be copies of all contstruc-
tion Contracts including required Performance and Payment Bonds.
A final inspection, attended by representatives for the Tenant, General Contractor,
host Airline (if applicable), and Airport Board, will be performed on all projects prior
to approval of completed work and/or issuance of a Certificate of Occupancy. One
set of reproducible, mylar, as-built drawings is required at final inspection prior to is-
suance of a final Certificate of Occupancy.
The Applicant shall indemnify and hold harmless the Airport Board, the Cities of Dal-
las and Fort Worth, their governing officials, officers, agents, and employees, against
and from (a) the risk of injuries (including wrongful death) or damage direct or conse-
quential, to it or them or to its or their property, arising out of or in connection with
the performance of the work, and (b) the risk of claims and demands by third persons
arising or alleged to arise out of the performance of the work, whether such risk arise
out of acts or omissions of the Applicant. its contractors, the Airport Board, the Cities
of Dallas and Fort Worth, or otherwise.
The Applicant shall pay all claims lawfully made against it by Contractors, Subcon-
tractors, Materialmen, and Workmen, and all claims lawfully made against it by other
third persons arising out of or in connection with or because of the performance of
the work, and shall cause alt Contractors and Subcontractors to pay all such claims
lawfully made against them.
6. GRAPHICS APPLICATIONS FOR NON SIGNATORY AIRLINES - (Airlines not signa-
tory to Airport Use Agreement):
The Applicant shall deposit with the Airport's Director of Finance an amount equal
to 50% of the cost quotation specified on the reverse side of this form. This deposit
shall be held in escrow and applied to the cost of future removal of Graphics. Unused
funds held in escrow shall be returned to the Applicant upon release by the Director
of Planning and Engineering of any obligations associated with the Work.