September 20, 1993
Gary D. Atwood, Vice President
Austin Bridge and Road
D/FW Paving Division
2949 Stemmons Freeway
Suite 250
Dallas, Texas 75247
RE: Riverchase Drive II and III
Maintenance Bond Walk Through (9/20/93)
Mr. Atwood:
Attached you will find a preliminary walk through punch list for
the above referenced project. As you know, there is a two year
maintenance bond on the paving for this project; however, staff has
found the listed problems during a routine follow up and would like
to see them addressed as soon as possible.
Please contact me at 462-8495 to set up a time to follow up on the
repairs.
If you have any questions please don't hesitate to call.
Street Superintendent
RG/rg
cc: Steven G. Goram, Director of Public Works
Ken Griffin, city Engineer
Larry Davis, Construction Inspector
CZTY OF COPPELL
BOND WPJ.~K THROUGH
R~VERCH~E ~ & I~
SEPTF. KBER 20~ ~993
e
SEVERAL BUTTONS BROKEN OR MISSING AT TAPER AND THROUGH OUT
THE PROJECT·
RANDOM CRACK 3 PANELS SOUTH OF THE MEDIAN.
FIRE HYDRANT BUTTON MISSING
RANDOM CRACKS 7 PANELS NORTH OF PEBBLE CREEK DRIVE IN NORTH
BOUND LANE.
MAJOR CRACKING SOUTH OF INLETS NORTH OF STONECREST-POSSIBLE
CURB DRAINAGE AFFECTED.
CURB DAMAGE ON EAST SIDE ABOUT HALFWAY DOWN RIVERCHASE,
APPEARS THAT SOMEONE DID SOME EXPLORING BENEATH THE
PAVEMENT/A SINK HOLE CURRENTLY EXISTS·
RG/rg
RIVERWT.RG