ST8504-CS 880624The City With A Beautiful F
June 24, 1988
P,O, Box 478
Coppell, Texas 75019
214 - 462 - 0022
Jean Maier
Nathan D. Maier Consulting Eng., Inc.
Three Northpark
8800 N. Central Expwy.
Suite 300
Dallas, Texas 75231
RE: Final walk through inspection for -~.-~ ' ~ I
Dear Jean:
On 6/16/88, the City of Coppell. performed a final walk through
inspection for Riverchase Dr. Phase I. The following items will
need to be resolved prior to acceptance of this project:
Water Utility Department
5 + 00 Clean invert of manhole of marked curb
7 + 00 Valve on north side of street needs 4' extension
7 + 00 Valve on south side of street needs to be cleaned
out
9 + 50 Install plug in C. 0.
19 + 98 Locate Line "C" C. O.
12 + 00 Valve on north side of street needs 4' extension
]_5 + 00 Manhole Line "C" clean invert
17 + 00 Valve on north side of street needs 4' extension
10 + O0 Manhole Line "C" clean invert
22 + 00 Valve on north side of street needs 4' extension
24 + 55 (Fairway Dr.) Valve on north~side of street,
paint lid
27 + 00 Valve on north side of street needs 4' extension
33 + 55 Valve on south side of street needs to be reset
and needs 4' extension
Street Department
69 + 25 Patch and mud ball bole
Reseal expansion joint
59 + 90 Repair broken concrete rip-rap
Clean dirt out of pipe
38 + 89 Clean out both inlets
Fire Department
1) All fire hydrants need to be oiled
2) Fire hydrant 2 + 00 needs repainting
Developmental Inspections Department
1) Construction of wall on north side of Riverchase Drive
and golf course
2) Construction of sidewalk south side of Riverchase Drive
If you have any questions, please feel free to contact me at
462-8495.
Thank ~ou,
Steven M. Morton
Chief Developmentml~I~-pector
SMM/bb
cc: Steve Goram, Director of Public Works