ST8502-CS 861216CONTINENTAL
PIPE UNE COMPANY
1909 Southwood Drive~
Lake Charles, LA 70605
(318) 491-5855
December 16, 1986
Certified Mail #P018-669-929
Mr. Frank Trando
City Manager
P. O. Box 478
Coppell, Texas 75019
Dear Mr. Trando:
Modifications to the Con-Dot 6-inch products pipeline to accommodate the
City of Coppell's Moore Road construction at Belt Line Road were completed
on September 12. The final completed cost of the project is $13,954.10.
A summary of these costs are included on the enclosed invoice number
WWL0029.
We would appreciate payment within 30 days of the date of the invoice to
my attention at the above address. If you have any questions, please
contact me at (318) 491-5852, or Larry Weiler, the project engineer at
(318) 491-5867.
Sincerely,
David A. Vanderpool
District Engineer
111/20: LGW/sb
Con-Dor Pipe Line Company
P.O. Box 1267
Ponca City, OK 74603
The. City of Coppell
P.O. Box 478
Coppell, TX 75019
December 3, 1986
Invoice No. WWLO029
We 'charge your account for costs to concrete-coat and relocate our 6-inch products line to
accommodate construction by The City of Coppell. The construction is a new roadway next to
the existing Moore Road.
Materials
160' -8" of 6" concrete-coated pipe
1,753.66
Contract Services
Watkins Construction Company Inc.
Chemical Plant Services Inc.
H&H X-Ray Services Inc.
Federal Express
4,450.00
900.00
636.00
105.75
Company Expenses
Expense and mileage report--Larry Wailer
Salaries--Larry Wailer (136 hours)
Jay Jones (26 hours)
Employee Benefits ($2,073.22 x 30.33%)
Overhead--applled to direct company labor ($2,073.22 x 20.29%)
--applied to all costs ($12,459.02 x 12.00%)
Total amount due from The City of Coppell
1,490.77
1,569.44
503.88
628.84
420.68
1,495.08
$13,954.10
TCS:MG:clp
t2-03-86