ST8502-CS 861124GINN, INC. CONSULTING ENGINEERS November 24, 1986 Mr. alley Ashlar C~ntracting Co. P.O. Box ~3 Lewisville,~TX 75067 Re: December 1, 1986 Opening of Moore Road Southbound One-Way Dear Mr. Bailey: It is my opinion that Moore Road will not be ready to open December 1, 1986, as shown on the last schedule furnished from you for the following reasons: We had requested at the meeting on Moore Road, November 6, 1986, that ample time be available for us to reinspect, in case replacement is required. At this time, no date has been set for this reinspection. Also, there are some other areas of concern that have yet to be resolved, such as the pavement area around the two storm drain manholes and the counter sink at Swan Intersection. Also, before Moore Road can be open, PSI specifications must be met on any concrete pour that traffic will use. A more realistic date should be considered at this time. If these areas of concern can be resolved in the very near future, then December 8, 1986 would seem more of an appropriate date for the opening. Please consider the above information in establishing a date. Your response would be greatly appreciated. SinTerely, Walter M. Ellison /ss Ed Powellv/ Wayne Ginn Kevin Peiffer Randy Fleming Reuben Martinez 17103 Preston Road ® Suite 100 ® LB 118 ® Dallas, Texas 75248