ST8502-CS 861030GINN, INC. October 30, 1986 Ashlar Contracting Company Post Office Box 713 Lewisville, Texas 75067 CONSUL Attention: Mr. W. K. Wolfe, Jr. Re: Moore Road Improvements Dear Mr. Wolfe: For the record, you are reminded that the contract completion date on the above referenced project is November 1, 1986. Per the contract, liquidated damages are $750.00 per calendar day. With much concern, we strongly request that you expedite the remaining items of work yet to be completed on this project. We would be happy to assist you in reaching completion of this project by having required inspections requested and scheduled in advance to provide a smooth progression of work. For your information, St. Louis Southwestern Railway Company has advised us that we can expect to see the Mockingbird Lane crossing completed and opened by November 3, 1986. Based on this latest information, it now appears that it is possible to make Moore Road "ONE-WAY" southbound during the construction of the west side of Moore Road. We will be contacting you next week to finalize our earlier discussions on how the public is to be informed on this issue. Please contact our office if you have any questions. Sincerely, Kevin Peiffer KP:jc cc: Mayor & Council Frank Trando, Acting City Manager J. E. Powell, P.E., City Engineer H. Wayne Ginn, P.E. Butch Ellison Ray Bailey 16135 Preston Road · Suite 106 · Dallas, Texas 75248 · Phone 214/386-6611