Loading...
ST8502-CS 860613GINN, INC. June 13, 1986 CONSULTING ENGINEERS Mr. W. K. Wolfe, Jr. Ashlar Contracting Co. P.O. Box 713 Lewisville, TX 75067 We are in receipt of your June 2, 1986 letter and enjoy the opportunity to respond to the issues you have addressed. After reviewing your comments, we wonder if you have taken the time to familiarize yourself with the contract documents and specifications to which you are contractually obligated. We will clarify some of these areas which we feel are causing Ashlar Contracting Company to mislead themselves regarding its responsibilites on this project. On December 17, 1985, a preconstruction conference was held. The purpose of this meeting was to clarify each party's responsibilities and contractual obligations. A summary of what was discussed and ~kq~ upon was sent to you on January 2, 1986. Please refer to Item 4, page 2 of that summary which states the following: "Ashlar Contracting Company is responsible for notifying utility companies and coordinating work schedules with them on relocations, excavations, or any conflicts." The same issue is clearly defined in the Contract Documents and Specifications, Section 00650, paragraph 1.14 "Contractor's Responsibility for Utilities and Services," page 9, which states "In case that such physical properties (property of utility companies) conflict with the performance of the contract, it shall be the contractor's responsibility to ~1~.~~ such con- flicts and to give ~ notice thereof to the owners of the utility." Again, this same issue is .addressed tn Section 00650, ' item 4, page 12 Having paragragh 1.25, 'General Notes, · clarified this issue, it is an obvious observation that Ashlar should have fulfilled their own responsibilities and should have taken the initiative to contact GTE (incident per your letter) directly, instead of waiting for TP&L to do your work for you. As a result, Ashlar caused delay to themselves and their sub- contractors for three months. Also per your letter you stated that someone suggested:th&t~f you staked out the right-of-way limits for TP&L at the bridge, this would expedite TP&L to relocate their poles and that this cost Ashlar several hundred dollars to do and the poles were still not moved for several months. The suggestion you refer to was made at the preconstruction conference by TP&L. If the poles were not relocated in a sufficient tine frame and caused a delay, per the Contract Specifications, General Conditions of 16lXSPrc~:,n Ri)ad · Suite !06 · Dalla,,Texa5 75248 · Phone214/386-6611 Agreement, Section 4, paragraph 4.02, "Extension of Time," "the Contractor shall give the Engineer prompt notice in writing of the cause of such delay." No such notice was ever received by our office. Therefore, at the time, Ashlar must have felt this was only a minor inconvenience. In addition, to construct this project according to the plans, you needed to define the right-of-way limits, so we do not believe any additional costs were incurred staking the right-of-way. Also in your letter, you referenced Lone Star Gas - Transmission Department as showing very slow response on addressing conflicts with their utility. You are reminded that it was strongly emphasized at the preconstruction conference on December 17, 1985, by both Ginn, Inc. and Lone Star Gas that you needed to provide our office with certain existing utility information prior to the City and Lone Star Gas being able to begin their negotiations. Our office received this information on March 23, 1986. This three month delay is directly the result of Ashlar's lack of responsiveness. In regard to the 16" waterline conflict, you are correct that we received a price from Ashlar in April for this extra work. Since then we have been working closely with some of the property owners and the City regarding alternative solutions to the lowering of this water main. Please recall, however, that this extra work price was requested on February 12, 1986, and we finally received it on April 21, 1986. Throughout the decision making process required for the items you have addressed in your letter, there have been numerous other items which could have been worked on and have not. Those are storm sewer laterals, storm sewer inlets, and junction boxes. Due to this fact, we see no delays occurring yet on the project other than those you have been directly responsible for. Also, the temporary asphalt detours, if maintained properly (including drainage), should hold up very well and will continue to be needed until you complete the items of work just previously described. Per the Contract and as clarified at the preconstruction conference, Ashlar is reauired to provide a construction superintendent on the job at all times to manage the project. We are pleased to hear that you have been meeting your responsibility in this particular area. Please be aware that further delays can be anticipated if you do not submit the required shop drawings in a timely fashion. This was addressed on December 17, 1985, at the preconstruction conference and restated in our January 2, 1986 correspondence to you (see item 10, page 2 of that correspondence). To date, we have not received the required submittals. We must emphasize the necessity to submit the required shop drawings as soon as possible so that you do not create additional delays to yourselves in the coming months. Per your comment regarding "exposure to additional claims by the Public," until you complete the project, that exposure shall exist per the contract. Your realization of this fact will hopefully motivate you to complete the work as soon as possible. In response to your last paragraph on the second page related to "right-of-way not being obtained, slow payments, reduced payment, deleted item payments," we have the following comments. First, Ashlar Contracting Company has not been delayed or affected by any right-of-way issues whatsoever. No stop work order has ever been issued for any work within the limits of the public right-of-way. The City of Coppell controls the cash flow on this project and when a pay application is submitted in proper form and all the math is correct, the pay application is processed in a timely fashion. In regard to reduced or deleted payments, this is a unit price job and you have been paid for the proper percentage of units of work completed to date in accordance with contract requirements. Per your directions, we have requested to our structural engineer that he revise the south abutment cap design due to the new Shaft "D" location. Any additional fees incurred by the City of Coppell as a result of this design change will be charged to Ashlar Contracting Company. A bill will be sent to you and then a deduction for this extra design work shall be shown on the payment application. In summary, we hope this letter helps clarify the contractor's responsibilities and provides motivation to your staff to begin planning your work schedules ahead of time. Part of finding the solution to a problem is first defining what the problem is. Now that we have identified the problem, we trust you will initiate the means and methods to resolve the problems. We, too, feel a meeting is necessary and would like to schedule one at our office for Tuesday, June 17, 1986, at 9:00 a.m. If this time is not convenient, please advise. Sincerely, Kevin Peiffer /sr Ed Powell Wayne Ginn Randy Fleming Reuben Martinez