Keith Marvin - Old Town Coppell Updated Estimates and Review Meeting
From: Dan Prendergast <drp@freese.com>
To: "kmarvin@coppelltx.gov" <kmarvin@coppelltx.gov>
Date: 5/20/2011 10:39 AM
Subject: Old Town Coppell Updated Estimates and Review Meeting
CC: Tricia Hatley <thh@freese.com>
Attachments:Old Town Coppell Developer Costs.pdf; Old Town Coppell 90% Cost Summary.pdf;
Old Town Coppell Project Breakdown Exhibit.pdf
Keith,
Attached are the updated cost estimate spreadsheets and exhibit based on our conversation yesterday. I added
in the private on street parking to the developer costs. I also removed the electrical conduit (bethel to the
pavilion) from the developer costs.
David Beckman will be at the Utility Coordination meeting on Tuesday so he should be able to answer any
questions that you have about the street lighting at that meeting.
How does 3:30 on Thursday (5/26) work for you guys to have our 90% plan review meeting? Let us know and I’ll
set it up.
Have a great weekend
Dan Prendergast, E.I.T.
East Transportation/Infrastructure
Freese and Nichols, Inc.
1701 N. Market St., Suite 500
Dallas, Texas 75202
214-217-2216
www.freese.com
Please consider the environment before printing this message.
This electronic mail message is intended exclusively for the individual or entity to which it is addressed. This message, together with any attachment,
may contain the sender's organization's confidential and privileged information. The recipient is hereby notified to treat the information as confidential
and privileged and to not disclose or use the information except as authorized by sender's organization. Any unauthorized review, printing, retention,
copying, disclosure, distribution, retransmission, dissemination or other use of, or taking of any action in reliance upon, this information by persons or
entities other than the intended recipient is prohibited. If you received this message in error, please immediately contact the sender by reply email and
delete all copies of the material from any computer. Thank you for your cooperation.
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4DD644FDCity...10/24/2011
Old Town Coppel and Bethel Rd Cost Summary
ProjectEstimated Cost
Bethel$1,913,930.00
Old Town (Developer Portion)$1,336,751.00
Old Town (City Portion)$2,763,779.00
Old Town (Total)$4,100,530.00
Total Project$6,014,460.00
ÎÑÙÉÎÆÏÚÎÍÍØÑÑíËÔÇÜÉØ
ÔÏ×ËÜÊÉËÈÚÉÈËØÔÐÍËÎÇØÐØÏÉÊ
ÚÎÍÍØÑÑÉÅ
îÍÔÏÔÎÏÎ×íËÎÛÜÛÑØÚÎÏÊÉËÈÚÉÔÎÏÚÎÊÉ
ðÜÄ
ESTIMATORCHECKED BYACCOUNT NO
DRPCJPcpl09446
ITEMDESCRIPTIONQUANTITUNITUNIT PRICETOTAL
Y
DEVELOPER IMPROVEMENTS
16" Reinforced Concrete Driveways and Alleys4,828 SY$30.00$144,840.00
26" Reinforced Stamped Concrete Driveways107 SY$78.00$8,346.00
38" Reinforced Concrete Pavement with 6" Integral Curb (On Street Parking)4,139 SY$38.00$157,282.00
48" Lime Subgrade Treatment9,814 SY$2.80$27,479.20
5Lime TON206$145.00$29,883.63
621" RCP (CL IIII) LF1,594$50.00$79,700.00
724" RCP (CL III) LF51$65.00$3,315.00
84'x4' Grate Inlet EA9$2,200.00$19,800.00
94' SQUARE SDMH EA1$3,200.00$3,200.00
108" C900 DR 14 PVC Waterline2,016 LF$32.00$64,512.00
11Trench Safety LF2,016$1.50$3,024.00
12Domestic Water Service Installation with meter70 EA$2,500.00$175,000.00
13Domestic Water Service Installation (4")2 EA$5,000.00$10,000.00
14Irrigation Water Service Installation (2")1 EA$3,500.00$3,500.00
15Fire Service Installation (4")14 EA$10,000.00$140,000.00
16Fire Service Installation (6")1 EA$12,000.00$12,000.00
178" PVC Wastewater Pipe (SDR-35)1,395 EA$45.00$62,775.00
18Sanitary Sewer Manhole EA6$3,500.00$21,000.00
19Install New 6" Sewer Service3 EA$1,800.00$5,400.00
20Install New 4" Sewer Service67 EA$1,500.00$100,500.00
21Trench Safety EA1,395$1.50$2,092.50
222" PVC Conduit EA10,671$6.50$69,361.50
233" PVC Conduit EA420$7.50$3,150.00
244" PVC Conduit EA440$8.50$3,740.00
256" PVC Conduit EA4,397$10.00$43,970.00
2630"X48"X36" Pull Box EA3$750.00$2,250.00
274'x8'x4' Pull Box EA1$1,100.00$1,100.00
282'x3' Telecom Handhole EA3$500.00$1,500.00
2917"x30" Telecom Handhole22 EA$750.00$16,500.00
Developer Improvements Subtotal$1,215,220.83
SUBTOTAL:$1,215,221
CONTINGENCY10%$121,530
DEVELOPER TOTAL$1,336,751
Page 1 of 1
Old Town Coppell 90% Cost Estimate 5-13-11
90% SUBMITTAL