ST8502-CS 851216becember 16,'i985 Mr. George Miller Ashlar Contracting Co. P.O. Box 713 Lewisville, TX 75067 Re: Moore Road Improvements Notice To Proceed CONSULTING ENGINEERS Gentlemen: You are hereby issued a "Notice to Proceed" for the above referenced project, on or before January 6, 1986. This "Notice to Proceed" applies to all items of construction except the bridge. You will be issued a separate "Notice to Proceed" with construction as soon as the Change Order is approved by the City of Coppell. Contract time is 300 calendar days with a completion date of November 1, 1986. Liquidated damages are $750.00 per calendar day. A certificate of insurance must be received by our office prior to the start of any work on this project. We look forward to working with you on this project. you have any questions, please call. Should Sincerely, Kevin Peiffer /st cc: Frank Proctor Ed Powell Steve Pennington 16135 Preston Road · Suite 106 · Dallas, Texas 75248 · Phone 214/386-6611