George Marshall - Re: Deforest Road
From: George Marshall
To: Kelly
Date:6/16/2010 4:46 PM
Subject:Re: Deforest Road
Kelly,
At this point, yes. The plan is to begin construction in the 4th quarter of this year. We are in the process of
acquiring right-of-way from several homeowners. The franchise utilities are still in their design process. The
engineering department is currently reviewing the civil plans from our design engineer and they are a 95% set.
Thank You, George
>>> "Kelly" <kelly@dirtstriker.com> 6/16/2010 4:39 PM >>>
Hi Mr. Marshall,
th
Is the plan still on track for construction to begin 4 quarter? A lot of people in the neighborhood are curious.
Regards,
Kelly Revis
926 Deforest Rd.
From: Matt Steer [mailto:MSTEER@coppelltx.gov]
Sent: Thursday, February 04, 2010 5:06 PM
To: kelly@dirtstriker.com
Cc: George Marshall
Subject: Re: Fwd: Deforest Road
Kelly,
I am forwarding an update sent from our Engineer George Marshall.
Please contact him directly if you have any questions.
Thanks,
Matt
>>> George Marshall 2/4/2010 4:48 PM >>>
I am happy to give you an update. The Deforest Road Reconstruction project design phase has been moving at
a slow pace over the last few months due to some drainage design issues. However, we are excited to say that
we have come to a solution and we are moving forward! We will be giving the design engineer our review
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4C18FFEBCity...10/28/2011
Page 2 of 2
comments from their last submittal early next week. There will not be any major changes to the plans. The
design will incorporate a 28' wide concrete pavement section with a sidewalk on both the north and south sides
of the roadway along with a traffic signal at MacArthur. We expect the design to be complete by the end of the
2nd quarter. The process to acquire additional pieces of ROW has been started. Prior to construction of the road
we will need to have the franchise (power, gas, cable, telephone) utilities relocated. We anticipate construction
to begin the 4th quarter of this year.
Thank You,
George Marshall, PE
George Marshall, P.E.
City of Coppell
Engineering
972-304-3562
>>> Michael Garza 2/4/2010 3:30 PM >>>
George,
Can you help me out?
>>> "Kelly" <kelly@dirtstriker.com> 2/4/2010 1:42 PM >>>
Hi Matt,
I live in Windsor Estates and many of us are very curious to find out the status of repaving Deforest Road and
putting in a sidewalk. It seems years have gone by with nothing progressing. dead bodies are gonna start
piling up in the side ditches.
At Christmas we went to Houston to visit my husband's family - somehow you know our cousins Eric and Sylvia
Crowder - can't remember the story.but small world, huh? Eric's mom and my husband's dad are siblings.
Sylvia said you were looking to upgrade in Coppell - our house is for saleJ
Can you let me know what is going on with Deforest so I can share the gossip with the neighbors?
Thanks!
Kelly Revis
926 Deforest Road
Kelly@dirtstriker.com
No virus found in this incoming message.
Checked by AVG - www.avg.com
Version: 8.5.432 / Virus Database: 270.14.140/2621 - Release Date: 01/28/10 07:36:00
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4C18FFEBCity...10/28/2011