George Marshall - RE: DeForest
From: George Marshall
To: Dan DeGroot
Date:9/1/2010 3:02 PM
Subject:RE: DeForest
90s or 45s should work. I think we can work out the elevation change in the field. Larry will keep on top of
them. Keep the FH connection at the same point. I would rather feed off the 12 out in Deforest than the 8 on
Inglenook. Note that there is a FH in Inglenook. The reason for keeping this FH is due to the distance between
Inglenook & Prestwick.
>>> "DeGroot, Dan" <dan.degroot@burgessniple.com> 9/1/2010 2:49 PM >>>
Looks like we will have to put in some 90’s to go under the wall. Think the field guys would prefer feeding from
the east side of Inglenook. Plus valve would be on DeForest
From: George Marshall [mailto:gmarshall@coppelltx.gov]
Sent: Wednesday, September 01, 2010 2:23 PM
To: DeGroot, Dan
Subject: Re: DeForest
Per the asbuilt plans and field verification (today) there is a 6" valve directly next to the alley pavement. Why
don't you just remove the FH and shoot directly across the road on the original FH lead instead of installing a
new tap on the main?
Thank You, George
>>> "DeGroot, Dan" <dan.degroot@burgessniple.com> 9/1/2010 1:17 PM >>>
George: In the pdf is a a location where I need to know if the City has a valve for the hydrant. Also in the same
pdf you’ll see that I turned on the contours in the paving file. I was wondering if show the contours and placing
the flow arrows would be enough for the intersections.
Lowell D. DeGroot, P.E.
Senior Project Manager
Burgess & Niple, Inc.
11117 Shady Trail
Dallas, Texas 75229
972/620-1255 ext. 6016
Note:
These electronic documents are provided by Burgess & Niple (B&N) as a convenience to our clients.
The official document is available as a manually signed, initialed, or sealed hard copy. If there is a discrepancy between electronic files and the hard
copies, the hard copies shall prevail.
It is our professional opinion that this electronic information provides information current as of the date of its release. Any use of this information is at
the sole risk and liability of the user. The user is responsible for updating information to reflect any changes in the information following the
preparation date of this transmittal.
The delivery of this information in electronic format is for the benefit of the owner for whom the services have been performed. Nothing in the transfer
should be construed to provide any right to third parties to rely on the information provided, or that the use of this information implies the review and
approval of Burgess & Niple.
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4C7E6B0CCity...10/28/2011