Ken Griffin - RE: Old Town Coppell - Cost Estimates
From: Caleb Thornhill <bct@freese.com>
To: "KGRIFFIN@ci.coppell.tx.us" <KGRIFFIN@ci.coppell.tx.us>, Mindi Hurley <m...
Date: 3/16/2010 4:48 PM
Subject: RE: Old Town Coppell - Cost Estimates
CC: Tricia Hatley <thh@freese.com>, CPL09446 <CPL09446@freese.com>, DanPrend...
Ken/Mindi,
Meant to include this earlier with the cost estimate. The estimated additional fee will be approximately $31,500 to
design the remainder of the Old Town Coppell Infrastructure Improvements. Once you guys have had a chance to sit
down and verify the responsibilities of the City and the developer, we can sit down and discuss which route you guys
would like to take.
Hope this helps. Trish will be out the rest of this week. If you need anything else regarding this project, let me know.
Thanks.
B. Caleb Thornhill, P.E.
Freese & Nichols, Inc.
214-217-2282
From: Caleb Thornhill
Sent: Tuesday, March 16, 2010 11:10 AM
To: 'KGRIFFIN@ci.coppell.tx.us'; 'Mindi Hurley'
Cc: Tricia Hatley; 'cpl09446@freese.com'; Dan Prendergast
Subject: Old Town Coppell - Cost Estimates
Ken/Mindi,
Attached are the updated cost estimates for Old Town Coppell Infrastructure Improvements. The “New Format” is an
estimate for the infrastructure improvements in our current contract based on our discussion last week. The “Full Build
Out” is an estimate for all infrastructure improvements. Please review and let me know if you have any questions. If
you need additional information, feel free to call.
Thanks.
B. Caleb Thornhill P.E.
Project Manager
Freese and Nichols, Inc.
Main: 214-217-2200
Direct: 214-217-2282
Fax: 214-920-2565
Email: bct@freese.com
This electronic mail message is intended exclusively for the individual or entity to which it is addressed. This message, together with any attachment, may
contain the sender's organization's confidential and privileged information. The recipient is hereby notified to treat the information as confidential and privileged
and to not disclose or use the information except as authorized by sender's organization. Any unauthorized review, printing, retention, copying, disclosure,
distribution, retransmission, dissemination or other use of, or taking of any action in reliance upon, this information by persons or entities other than the intended
recipient is prohibited. If you received this message in error, please immediately contact the sender by reply email and delete all copies of the material from any
computer. Thank you for your cooperation.
file://C:\Documents and Settings\lhenderson\Local Settings\Temp\XPgrpwise\4B9FB661...11/17/2011
(11/17/2011) Ken Griffin - Old Town Coppell - Cost EstimatesPage 1
From:
Caleb Thornhill <bct@freese.com>
To:
"KGRIFFIN@ci.coppell.tx.us" <KGRIFFIN@ci.coppell.tx.us>, Mindi Hurley <m...
CC:
Tricia Hatley <thh@freese.com>, CPL09446 <CPL09446@freese.com>, DanPrend...
Date:
3/16/2010 11:16 AM
Subject:
Old Town Coppell - Cost Estimates
Attachments:
Old Town OPCC-New Format 3-12-10.pdf; Old Town OPCC-New Format-FULL BUILD-
OUT3-12-10.pdf
Ken/Mindi,
Attached are the updated cost estimates for Old Town Coppell Infrastructure Improvements. The "New
Format" is an estimate for the infrastructure improvements in our current contract based on our
discussion last week. The "Full Build Out" is an estimate for all infrastructure improvements. Please
review and let me know if you have any questions. If you need additional information, feel free to call.
Thanks.
B. Caleb Thornhill P.E.
Project Manager
[cid:image001.jpg@01CAC4F8.9FC98C80]
Freese and Nichols, Inc.<http://www.freese.com/>
* Main: 214-217-2200
* Direct: 214-217-2282
* Fax: 214-920-2565
* Email: bct@freese.com<mailto:bct@freese.com>
________________________________
This electronic mail message is intended exclusively for the individual or entity to which it is addressed.
This message, together with any attachment, may contain the sender's organization's confidential and
privileged information. The recipient is hereby notified to treat the information as confidential and
privileged and to not disclose or use the information except as authorized by sender's organization. Any
unauthorized review, printing, retention, copying, disclosure, distribution, retransmission, dissemination or
other use of, or taking of any action in reliance upon, this information by persons or entities other than the
intended recipient is prohibited. If you received this message in error, please immediately contact the
sender by reply email and delete all copies of the material from any computer. Thank you for your
cooperation.
(11/17/2011) Ken Griffin - Old Town OPCC-New Format-FULL BUILD-OUT3-12-10.pdfPage 1
OLD TOWN COPPELL -FULL BUILD OUT
INFRASTRUCTURE IMPROVEMENTS
COPPELL, TX
OPINION OF PROBABLEC ONSTRUCTION COST
ARCH
M12,2010
ESTIMATORCHECKED BYACCOUNT NO
DRPCPL09446
ITEMDESCRIPTIONQUANTITYUNITUNIT PRICETOTAL
PAVING IMPROVEMENTS
8" Reinforced Concrete Pavement 13,600SY$35.00$476,000.00
8" Reinforced Stamped Concrete Pavement 850SY$105.00$89,250.00
Remove and Dispose of Existing Asphalt (Bethel) 1,500SY$6.00$9,000.00
Asphalt Transition 560SY$20.00$11,200.00
8" Lime-Cement Stabilized Subgrade 14,960SY$3.00$44,880.00
On-Street Parking 9,110SY$29.00$264,190.00
Median Nose 4EA$1,200.00$4,800.00
Monolithic Curb as part of Median Structures 200LF$25.00$5,000.00
Lime (Hydrated) 202TN$135.00$27,264.60
Temporary Pavement for Traffic Control (2" HMAC, 6" Agg, Base) 1,000SY$135.00$135,000.00
Traffic Signs 15EA$410.00$6,150.00
Pavement Markings 8,500LF$1.25$10,625.00
Concrete Sidewalk 24,000SF$4.20$100,800.00
Solid Pavement Markings 240LF$4.00$960.00
Handicap Symbols 18EA$150.00$2,700.00
Parking Space Striping 5,920LF$0.60$3,552.00
Intersection Signalization (Bethel Rd & Main St) 1LS$150,000.00$150,000.00
Paving Item Subtotal$1,341,371.60
DRAINAGE IMPOVEMENTS
18" RCP 200LF$40.00$8,000.00
24" RCP 800LF$45.00$36,000.00
30" RCP 250LF$55.00$13,750.00
36" RCP 900LF$65.00$58,500.00
Trench Safety & Support 2,150LF$1.25$2,687.50
10' Curb Inlet 9EA$2,500.00$22,500.00
15' Curb Inlet 2EA$3,500.00$7,000.00
4' SDMH 2EA$4,000.00$8,000.00
30" Headwall 1EA$3,500.00$3,500.00
Rock Rip Rap 12SY$80.00$960.00
Drainage Grading Improvements 1LS$50,000.00$50,000.00
Drainage Item Subtotal$210,897.50
UTILITY IMPROVEMENTS
10" PVC C-900 945LF$35.00$33,075.00
8" PVC C-900 3,065LF$30.00$91,950.00
6" PVC C-900 290LF$28.00$8,120.00
8" Gate Valve 9EA$500.00$4,500.00
Fire Hydrant 10EA$3,000.00$30,000.00
16"x10" TS&V 2EA$5,000.00$10,000.00
16"x8" TS&V 2EA$4,800.00$9,600.00
10"x8" TS&V 2EA$4,500.00$9,000.00
8"x6" TS&V 2EA$4,000.00$8,000.00
Fittings and Bends 2TN$2,500.00$5,000.00
Water Service Connection (short) 7EA$650.00$4,550.00
Water Service Connection (long) 9EA$900.00$8,100.00
8" PVC SDR-35 (Sanitary Sewer) 2,545LF$40.00$101,800.00
Sewer Service Connection (short) 19EA$600.00$11,400.00
Sewer Service Connection (long) 1EA$900.00$900.00
Manholes 11EA$3,500.00$38,500.00
Trench Safety & Support 6,845LF$1.25$8,556.25
Utility Item Subtotal$383,051.25
LANDSCAPE AND IRRIGATION IMPROVEMENTS
Landscape Planting (3" Cal, 8' HT, 5' Spread) 51EA$1,984.00$101,184.00
Landscape Planting (shrubs, etc) 77EA$600.00$46,200.00
Planters 40EA$800.00$32,000.00
Irrigation System 1LS$35,000.00$35,000.00
Street Lighting Assembly 42EA$3,000.00$126,550.00
Street Lighting Foundation 42EA$750.00$31,637.50
2" PVC Electrical Conduit 2,531LF$8.89$22,500.59
Landscape Item Subtotal$395,072.09
SUBTOTAL:$2,330,400
CONTINGENCY20%$466,080
PROJEC OL$2,796,500
TTTA
Developer's Responsibility
On-Street Parking 4,300SY$29.00$124,700.00
Water Service Connection (short) 7EA$650.00$4,550.00
Water Service Connection (long) 9EA$900.00$8,100.00
Sewer Service Connection (short) 19EA$600.00$11,400.00
Sewer Service Connection (long) 1EA$900.00$900.00
Developer Total$149,650
CIY OF COPPELL OL$2,646,850
TTTA
Page 1 of 1
OdTownOPCC-NewFora-FULLBULD-OUT3-12-10xsx
l mt I.l
(11/17/2011) Ken Griffin - Old Town OPCC-New Format 3-12-10.pdfPage 1
OLD TOWN COPPELL -ORIGINAL SCOPE
INFRASTRUCTURE IMPROVEMENTS
COPPELL, TX
OPINION OF PROBABLE CONSTRUCTION COST
MARCH 12, 2010
ESTIMATORCHECKED BYACCOUNT NO
DRPCPL09446
ITEMDESCRIPTIONQUANTITYUNITUNIT PRICETOTAL
PAVING IMPROVEMENTS
8" Reinforced Concrete Pavement 9 ,450SY$35.00$330,750.00
8" Reinforced Stamped Concrete Pavement 7 00SY$105.00$73,500.00
Remove and Dispose of Existing Asphalt (Bethel) 1 ,500SY$6.00$9,000.00
Asphalt Transition 5 60SY$20.00$11,200.00
8" Lime-Cement Stabilized Subgrade 10,395SY$3.00$31,185.00
On-Street Parking 6 ,800SY$29.00$197,200.00
Median Nose 4 EA$1,200.00$4,800.00
Monolithic Curb as part of Median Structures 2 00LF$25.00$5,000.00
Lime (Hydrated) 1 40TN$135.00$18,944.89
Temporary Pavement for Traffic Control (2" HMAC, 6" Agg, Base) 1 ,000SY$135.00$135,000.00
Traffic Signs 1 5EA$410.00$6,150.00
Pavement Markings 7 ,500LF$1.25$9,375.00
Concrete Sidewalk 24,000SF$4.20$100,800.00
Solid Pavement Markings 2 40LF$4.00$960.00
Handicap Symbols 1 2EA$150.00$1,800.00
Parking Space Striping 5 ,700LF$0.60$3,420.00
Intersection Signalization (Bethel Rd & Main St) 1 LS$150,000.00$150,000.00
Paving Item Subtotal$1,089,084.89
DRAINAGE IMPOVEMENTS
18" RCP 1 40LF$40.00$5,600.00
24" RCP 5 60LF$45.00$25,200.00
30" RCP 1 75LF$55.00$9,625.00
36" RCP 6 30LF$65.00$40,950.00
Trench Safety & Support 1 ,505LF$1.25$1,881.25
10' Curb Inlet 9 EA$2,500.00$22,500.00
15' Curb Inlet 2 EA$3,500.00$7,000.00
4' SDMH 2 EA$4,000.00$8,000.00
30" Headwall 1 EA$3,500.00$3,500.00
Rock Rip Rap 1 2SY$80.00$960.00
Drainage Grading Improvements 1 LS$50,000.00$50,000.00
Drainage Item Subtotal$175,216.25
UTILITY IMPROVEMENTS
10" PVC C-900 9 45LF$35.00$33,075.00
8" PVC C-900 2 ,670LF$30.00$80,100.00
6" PVC C-900 1 40LF$28.00$3,920.00
8" Gate Valve 7 EA$500.00$3,500.00
Fire Hydrant 8 EA$3,000.00$24,000.00
16"x10" TS&V 2 EA$5,000.00$10,000.00
16"x8" TS&V 1 EA$4,800.00$4,800.00
10"x8" TS&V 2 EA$4,500.00$9,000.00
8"x6" TS&V 2 EA$4,000.00$8,000.00
Fittings and Bends 2 TN$2,500.00$5,000.00
Water Service Connection (short) 4 EA$650.00$2,600.00
Water Service Connection (long) 7 EA$900.00$6,300.00
8" PVC SDR-35 (Sanitary Sewer) 1 ,910LF$40.00$76,400.00
Sewer Service Connection (short) 5 EA$600.00$3,000.00
Sewer Service Connection (long) 1 EA$900.00$900.00
Manholes 7 EA$3,500.00$24,500.00
Trench Safety & Support 5 ,665LF$1.25$7,081.25
Utility Item Subtotal$302,176.25
LANDSCAPE AND IRRIGATION IMPROVEMENTS
Landscape Planting (3" Cal, 8' HT, 5' Spread) 5 1EA$1,984.00$101,184.00
Landscape Planting (shrubs, etc) 7 7EA$600.00$46,200.00
Planters 4 0EA$800.00$32,000.00
Irrigation System 1 LS$35,000.00$35,000.00
Street Lighting Assembly 4 2EA$3,000.00$126,550.00
Street Lighting Foundation 4 2EA$750.00$31,637.50
2" PVC Electrical Conduit 2 ,531LF$8.89$22,500.59
Landscape Item Subtotal$395,072.09
SUBTOTAL:$1,961,550
CONTINGENCY20%$392,310
PROJECT TOTAL$2,353,900
Developer's Responsibility
On-Street Parking 2 ,675SY$29.00$77,575.00
Water Service Connection (short) 4 EA$650.00$2,600.00
Water Service Connection (long) 7 EA$900.00$6,300.00
Sewer Service Connection (short) 5 EA$600.00$3,000.00
Sewer Service Connection (long) 1 EA$900.00$900.00
Developer Total$90,375
CITY OF COPPELL TOTAL$2,263,525