Re-
Denton Tap Road Improvements from Sandy Lake Road to Denton
Creek - ABQ Median Opening Request
Dear Mr. Doyle:
This letter is in response to your letter concerning the above.
The design of the requested~ median opening north of Parkway Blvd.
can be included in the scope of our work covering overall design
of the project, and therefore you will not have to go through the
work authorization process.
The procedure for accomplishing this is as follows:
Obtain a letter of Financial Commitment from ABQ
Development Company stating that they will pay for the
Engineering, Testing, Inspection, and Construction of
the Median Opening. This letter should state that they
will deposit the funds with the City within 5 days after
the City Council approves a Change order covering the
construction of the Median Opening.
Upon receipt of the above letter of Financial
Commitment, you can authorize Ginn, Inc. to prepare a
Change Order for City Council consideration.
We have enclosed cost estimates for the. Change Order and
additional engineering costs. We are prepared to seek the
Contractor's approval of the necessary Change Order, and revise
the drawings accordingly upon receipt of your authorization.
We have also enclosed a letter of response for your signature on
City of Coppell letterhead to Jerry Parche' Consulting Engineers
which covers the above.
Please call me if you have any questions.