ST8402-CS 881222GINN, INC.
December 22, 1988
Mr. David N. Snyder, P.E.
L. H. Lacy Company
10888 Shady Trail
P.O. Box 541297
Dallas, Texas 75354-1297
Re: Denton Tap Road
Creek
Dear Mr. Snyder:
CONSULTING ENGINEERS
from Sandy ~ke Roaa ~o uen~on
Earlier today I hand delivered six sets of the revised Drawings
in the accompanying Drawing List which reflect the following:
1. Redesign of the irrigation connections and the addition
of irrigation sleeves for future irrigation piping,
power and control wiring between medians and the outside
back of curb at the locations indicated.
Addition of 2" PVC Conduits for future street lighting
and traffic signal installations.
Addition of double 3" PVC Conduits at the Parkway Blvd.
intersection for the future traffic signal installation.
This work is to be accomplished in accordance with the existing
unit prices in the Contract with the exception of the double 3"
and the single 4" Schedule 40 PVC Conduit. The 4" conduit will
be installed as Pay Item 618.3 at the unit price of $3.73 per
lineal foot as proposed in your November 28, 1988 letter, copy
attached. The double 3" conduit will be covered at a later date
when a unit price has been agreed upon. Please insert the
revised Drawings transmitted herewith in your construction sets
and remove their previous' counterparts from the project site.
As you can see fro emt~~.~ tabulation, this Field Change
stimated e Estimated Contract Price by
~ ~ Payment wi sed on the actual quantities of
installed.
If-you have any questions please call me.
Sincerely,
Karlsruher, P.E.
attachments
cc: Ginn, P.E.
Randy Fleming
j379 (j 379fc5)
17103 Preston Road · Suite 100 · LB 118 · Dallas, Texas 75248 · Phone 214/248-4900
8hee~
22
24
25
26
27
28
29
DENTON TAP RO~D IMPROVEMENTS
FROM 8~IDY ~ RO~D TO DENTON CREEK
FIELD C]I~I~iGE NO. 5
Description
Sheet Index and Summary o£
Quantities
Drainage Sra. 166+58 to 199+00
Drainage Sra. 169+00 to 174+00
Drainage Sra. 174+00 to 179+00
Drainage Sra. 179+00 to 184+00
Drainage Sra. 184+00 to 189+00
Drainage Sra. 189+00 to 194+00
Drainage Sta. 194+00 to 199+00
Drainage Sta. 199+00 to 204+00
Revision
NO.
4
1
2
2
2
3
4
4 & 5
2
582.4
618.1
618.2
618.3
TABULATION - FIELD CHANGE NO.
UNIT CHANGE IN
DESCRIPTION PRICE QUANTITY
Irrigation $848.00 (2) ea
connection
2" PVC conduit $ 2.40 2,062 if
(Sch. 40)
3" PVC conduit $ 3.00 307 if
($ch. 40)
4" PVC conduit $ 3.73 380 if
(Sch. 40)
CHI~NGE IN
COST
($1,696.00)
$4,948.80
$ 921.00
$1,417.40
TOTAL CHANGE IN ESTIMATED CONTRACT PRICE
$5,591.20