WA9901-CN031113 (2)CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
PROJECT: Meadowcreek / Rolling Hills Water Line Installation Project # WA 99 -01
CONTRACTOR: Site Concrete, Inc.
OWNER: City of Coppell
CHANGE ORDER NO.: Two (2)
DATE: October 31, 2003
Item Description Quantity Unit Unit Price Total
ADD:
New
Sawcut (full depth)
27
LF
3.45
93.15
New
Concrete Removal
474
SF
1.15
545.10
New
Concrete Replacement
474
SF
4.60
2,180.40
Total Revision to Contract Amount $2,818.65
Previous contract amount $353,200.00
Net increase in contract amount $2,818.65
Revised contract amount $356,018.65
Net increase in contract time of completion N/A
Revised Contract time of completion N/A
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full
accord and satisfaction of all past and future liability originating under any clause in the Contract by
reason of this revision to the Contract.
i /• S
Recommended y City Engineer Date
Approve, y City Manager Date
Agreed o by Contractor Date