WA9901-CN031113 (2)CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT: Meadowcreek / Rolling Hills Water Line Installation Project # WA 99 -01 CONTRACTOR: Site Concrete, Inc. OWNER: City of Coppell CHANGE ORDER NO.: Two (2) DATE: October 31, 2003 Item Description Quantity Unit Unit Price Total ADD: New Sawcut (full depth) 27 LF 3.45 93.15 New Concrete Removal 474 SF 1.15 545.10 New Concrete Replacement 474 SF 4.60 2,180.40 Total Revision to Contract Amount $2,818.65 Previous contract amount $353,200.00 Net increase in contract amount $2,818.65 Revised contract amount $356,018.65 Net increase in contract time of completion N/A Revised Contract time of completion N/A The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. i /• S Recommended y City Engineer Date Approve, y City Manager Date Agreed o by Contractor Date