ST0501-CS111213 (2) ID Task Name Duration Start Finish c 25, ' Jan 22, ' Feb 19,' Mar 18, ' Apr 15, ' May 13, ' Jun 10, ' Jul 8, '12 Aug 5, '1 Sep 2, '1 Sep 30, 0
1 Phase 1 125 days Mon 1/9/12 Fri 6/29/12 W I S I T I M F T I S W S T M F T S W S T M F T S W S I T M F TS
j
2 Barricades 2 days Mon 1/9/12 Tue 1/10/12
3 Erosion Control 3 days Wed 1/11/12 Fri 1/13/12
4 Prep R.O.W. 10 days Mon 1/16/12 Fri 1/27/12 -
5 Water Adjustments 5 days Mon 1/30/12 Fri 2/3/12
- 6 Storm Drain 40 days Mon 1/30/12 Fri 3/23/12 -
7 Saniitary Sewer 1 day Mon 2/6/12 Mon 2/6/12 T
L
8 Removals 10 days Mon 3/26/12 Fri 4/6/12
9 Excavation / Fill 10 days Mon 4/9/12 Fri 4/20/12 _
10 Retaining Walls 30 days Mon 1/30/12 Fri 3/9/12 T
I.
11 Rail 25 days Mon 3/12/12 Fri 4/13/12
liv
12 Lime Stabilization 10 days Mon 4/23/12 Fri 5/4/12
13 Concrete Paving 10 days Mon 5/7/12 Fri 5/18/12 _
Iv
14 Intersections 10 days Mon 5/21/12 Fri 6/1/12
- 15 Driveways 10 days Mon 5/21/12 Fri 6/1/12 T -
16 Inlet Tops 10 days Mon 5/21/12 Fri 6/1/12 7
17 Sidewalks & Ramps 10 days Mon 6/4/12 Fri 6/15/12
T
18 Backfill 5 days Mon 6/18/12 Fri 6/22/12
—.
19 Landscaping 5 days Mon 6/25/12 Fri 6/29/12 -
20
21 Phase!! 22 days Mon 7/2/12 Tue 7/31/12
22 Removals 1 day Mon 7/2/12 Mon 7/2/12 T
- 23 Excavation 1 day Mon 7/2/12 Mon 7/2/12
, I
Task Milestone ♦ External Tasks
Project: Pr12 Split Summary External Milestone
/13
Date: Tue 12/13/11
Progress Project Summary Deadline
Page 1
ID Task Name Duration Start Finish c 25, ' Jan 22, ' Feb 19, ' Mar 18, ' Apr 15, ' May 13, ' Jun 10, ' Jul 8, '121 Au g 5, '1 Sep 2, '1 Sep 30, ' 0
W S T M F T S W S T M F T S W S T M F T) S W S T M F T S_'
24 Lime Stabilization 4 days Tue 7/3/12 Fri 7/6/12 rl
25 Concrete Paving 5 days Mon 7/9/12 Fri 7/13/12 1
26 Removals 1 day Mon 7/16/12 Mon 7/16/12
27 Excavation 1 day Mon 7/16/12 Mon 7/16/12
28 j Lime Stabilization 4 days Tue 7/17/12 Fri 7/20/12 ,
29 Concrete Paving 5 days Mon 7/23/12 Fri 7/27/12 ,
30 Intersection 2 days Mon 7/30/12 Tue 7/31/12
31 Inlet Tops 2 days Mon 7/30/12 Tue 7/31/12
32 Driveways 2 days Mon 7/30/12 Tue 7/31/12
33
34 Phase III 85 days Tue 7/3/12 Mon 10/29/12
35 Removals 10 days Tue 7/3/12 Mon 7/16/12 -
36 Excavation 5 days Tue 7/17/12 Mon 7/23/12
1
37 Lime Stabilization 10 days Tue 7/24/12 Mon 8/6/12 -j.
38 Concrete Paving 10 days Tue 8/7/12 Mon 8/20/12 1�1
39 Intersections 10 days Tue 8/21/12 Mon 9/3/12 '■
40 Driveways 10 days Tue 8/21/12 Mon 9/3/12 '■
41 Inlet Tops 10 days Tue 8/21/12 Mon 9/3/12 '■
42 Sidewalk & Ramps 15 days Tue 9/4/12 Mon 9/24/12
43 Sidewalk Walls 15 days Tue 9/25/12 Mon 10/15/12
44 Signals 30 days Tue 8/21/12 Mon 10/1/12
45 Backfill 5 days Tue 10/16/12 Mon 10/22/12
— 46 A Landscaping 5 days Tue 10/23/12 Mon 10/29/12
Task i , Milestone ♦ External Tasks r
Project: Project1 Split Summary 9 1 . 1 . 1111111111 M9 1 External Milestone
Date: Tue 12/13/11
Progress Project Summary 9 Deadline
Page 2