George Marshall - Re: Coppell Impact Fees - Cost Estimates
From: Brandon Huxford <bjh@freese.com>
To: "gmarshall@coppelltx.gov" <gmarshall@coppelltx.gov>
Date: 11/21/2011 1:34 PM
Subject: Re: Coppell Impact Fees - Cost Estimates
CC: Tricia Hatley <thh@freese.com>
Attachments:ST0502A-EM050131-Freeport Pkwy Ruby to Sandy Lake.pdf; ST0502B-EM050131-
Freeport Pkwy Sandy Lake to 121.pdf; comments from George-10-5-11.xls
George,
Along the same lines as the previous email, I just wanted to verify the cost for Freeport Parkway - Sandy Lake
to SH 121 as well as Freeport Parkway - Ruby to Sandy Lake. In a previous markup the costs were stated to
have been:
Freeport Parkway (Sandy Lake to SH 121) – 20% of 8,370,421 = $1,674,084
Freeport Parkway (Sandy Lake to Ruby) – 20% of 5,150,000 = $1,030,000
On, the other hand the estimates are shown to be:
Freeport Parkway (Sandy Lake to SH 121) – Total City Cost - $1,140,436
Freeport Parkway (Sandy Lake to Ruby) – Total City Cost - $1,627,609
Have the estimates been revised since 2005? If so, could we get a copy of the revised estimate?
Thanks in advance,
Brandon Huxford, E.I.T.
Transportation/Infrastructure
Freese and Nichols, Inc.
1701 N. Market St. Suite 500
Dallas, Texas 75202
214-217-2335
214-217-2201 fax
www.freese.com
From: George Marshall [mailto:gmarshall@coppelltx.gov]
Sent: Monday, October 31, 2011 4:17 PM
To: Brandon Huxford
Cc: Tricia Hatley
Subject: Re: Coppell Impact Fees - Cost Estimates
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4ECA5383City...12/19/2011
Page 2 of 2
Attached are the estimates for Freeport projects. I will need to get back to you on the Sandy Lake projects.
Thank You, George
George Marshall, PE
City of Coppell
Engineering
972-304-3562
>>> Brandon Huxford <bjh@freese.com> 10/31/2011 2:35 PM >>>
George,
We are starting to compile data for the Roadway Impact Fees, would you happen to have cost estimates for
the projects you provided cost feedback on a couple weeks ago?
-Sandy Lake Road (Coppell Rd to Denton Tap Road) - $8,500,000
-Freeport Pkwy (SH 121 to Sandy Lake Rd) - $1,674,084
-Freeport Pkwy (Ruby Rd to Sandy Lake Rd) - $1,030,000
Thanks in advance.
Brandon Huxford, E.I.T.
Transportation/Infrastructure
Freese and Nichols, Inc.
1701 N. Market St. Suite 500
Dallas, Texas 75202
214-217-2335
214-217-2201 fax
www.freese.com
Please consider the environment before printing this message.
This electronic mail message is intended exclusively for the individual or entity to which it is addressed. This message, together with any attachment,
may contain the sender's organization's confidential and privileged information. The recipient is hereby notified to treat the information as confidential
and privileged and to not disclose or use the information except as authorized by sender's organization. Any unauthorized review, printing, retention,
copying, disclosure, distribution, retransmission, dissemination or other use of, or taking of any action in reliance upon, this information by persons or
entities other than the intended recipient is prohibited. If you received this message in error, please immediately contact the sender by reply email and
delete all copies of the material from any computer. Thank you for your cooperation.
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4ECA5383City...12/19/2011
Page 1 of 1
George Marshall - Re: Coppell Impact Fees - Cost Estimates
From: Rhonda Adloo
Subject: Re: Coppell Impact Fees - Cost Estimates
>>> Michael Garza 11/21/2011 2:12 PM >>>
Brandon,
This is the correct cost:
Freeport Parkway (Sandy Lake to SH 121) – 20% of 8,370,421 = $1,674,000
Freeport Parkway (Sandy Lake to Ruby) – 20% of 5,150,000 = $1,030,000
thanks,
Mike
about:blank12/19/2011
CIP Projects Status
Project #RoadwayFromToStatusCostCOST w/ FINANCINGNotes
1Sandy Lake RoadCity Limit (west)Coppell RoadCompleted$ 3,800,263.33
Estimate - $8,500,000 (split into 2 phases)
2Sandy Lake RoadCoppell RoadDenton Tap RoadCIP
5Royal LaneSandy Lake RoadExtend SouthCompletedPart of ST99-02 W. Sandy Lake Road +/-1350' Meeting notes say complete - don't have estimate
Estimate - $8,370,421
6Freeport PkwySH 121Sandy Lake RoadCIP(City Responsible for 20%)
Estimate - $5,150,000
7Freeport PkwyRuby RoadSandy Lake RoadCIP(City Responsible for 20%)
9Bethel RoadCity Limit (west)Freeport PkwyCompleted$ 7,280,320.90
added one southbound lane - Nothing done or any plans in the works
10Royal LaneIH 635Bethel Road??
11Southwestern BlvdCoppell RoadDenton Tap RoadCompleted$ 1,204,348.91
added one southbound lane - is cost provided for one lane? - Yes, actual construction cost.
13Macarthur BlvdBethel School RoadBelt Line RoadCompleted$ 325,393.65
?'s
What about added capacity for Bethel Road at Denton Tap?
We are adding traffic signal to MacArthur & Deforest along with additional turn lane on westbound Deforest.
Why are you not including any of the Coppell Road projects?
Page 1 of 1
George Marshall - Sandy Lake
From: "Chris B. Seely" <cseely@tnp-online.com>
To: <gmarshall@coppelltx.gov>
Date: 11/21/2011 5:47 PM
Subject: Sandy Lake
Attachments: B1 - North Coppell to South Coppell.pdf
George:
Attached is the OPC for the section between North Coppell and South Coppell. I haven’t been able to locate the
one for the section from South Coppell to Denton Tap. I will keep looking and have something for you tomorrow
morning.
Chris
Chris Seely, P.E.
(TX)
Project Manager
TEAGUE NALL AND PERKINS, INC
.
12160 North Abrams Road Suite 508
Dallas, Texas 75243
214.461.9867 phone
214.461.9864 fax
cseely@tnp-online.com
www.tnp-online.com
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4ECA8EAACit...12/19/2011
TEAGUE NALL AND PERKINS, INC.
OPINION OF PROBABLE COST
West Sandy Lake Road - Coppell Road North to Coppell Road South
Construction Standard: City of Coppell
Construction Date: 2011
ITEM
NO.DESCRIPTION OF ITEMSQUANTITYUNITUNIT COSTTOTAL
PAVING IMPROVEMENTS
1RIGHT-OF-WAY PREPARATION$2,500.00$50,000
20STA
2MOBILIZATION1LS$150,000.00$150,000
3CONCRETE REMOVAL$7.00$16,450
2350SY
4HMAC REMOVAL5400SY$7.00$37,800
5UNCLASSIFIED STREET EXCAVATION$12.00$240,000
20000CY
68" CEMENT STABLIZED SUBGRADE13600SY$2.50$34,000
7CEMENT STABLIZATION (42#/SY)$115.00$33,350
290TON
88" REINFORCED CONCRETE PAVEMENT13000SY$40.00$520,000
98" ENHANCED PAVEMENT$75.00$15,000
200SY
10REMOVE 6" HMAC PAVEMENT TRANSITION1100SY$7.00$7,700
11STEPPED BLOCK RETAINING WALLS$50.00$75,000
1500SF
12PVC CONDUIT2000LF$8.00$16,000
13PAVEMENT MARKINGS AND SIGNAGE$15,000.00$15,000
1LS
14BARRICADES, SIGNS & TRAFFIC CONTROL1LS$75,000.00$75,000
15EROSION CONTROL$25,000.00$25,000
1LS
168' BIKE PATH13000SF$6.00$78,000
175' SIDEWALK$5.00$45,750
9150SF
18BARRIER FREE RAMP6EA$1,000.00$6,000
19STREET LIGHT FOUNDATION$2,000.00$40,000
20EA
20RESTORE PARKWAYS20STA$2,500.00$50,000
21RESTORE/RECONSTRUCT EXISTING IRRIGATION$25,000.00$25,000
1LS
SUBTOTAL PAVING
$1,555,050
BRIDGE
1DEMO EXISTING BRIDGE$50,000.00$50,000
1EA
2FLEXIBLE BASE$55.00$15,400
280CY
318" DRILL PIERS152LF$100.00$15,200
430" DRILLED PIERS$150.00$56,250
375LF
5CONCRETE ABUTMENTS105CY$525.00$55,125
6CONCRETE BENTS$525.00$43,575
83CY
78" THICK BRIDGE DECK13004SF$18.00$234,072
8EXPOXY WATERPROOFING$2.50$9,125
3650SF
9CONCRETE SURFACE TREATMENT12716SF$2.50$31,790
10TYPE C PRESTRESSED CONCRETE GIRDERS$110.00$173,910
1581LF
11CONCRETRE RIP-RAP175CY$265.00$46,375
12STRUCTURAL STEEL - ARMOR JOINT$4.00$25,600
6400LB
13SPECIAL TRAFFIC / PEDESTRIAN RAIL193LF$155.00$29,915
14SPECIAL TRAFFIC / BICYCLE RAIL$210.00$81,060
386LF
15CONCRETE APPROACH SLABS144CY$450.00$64,800
16METAL BEAM GUARD FENCE$30.00$12,000
400LF
17ELECTRICAL CONDUIT880LF$8.00$7,040
18LIGHT STANDARDS$2,000.00$8,000
4EA
19ENHANCED PAVEMENT2175SF$8.00$17,400
SUBTOTAL BRIDGE
$976,637
WATER
1RELOCATE / ADJUST 24" WATER LINE$150.00$22,500
150LF
2RELOCATE MISC. WATER (HYDRANTS, VALVES, ETC)1LS$25,000.00$25,000
SUBTOTAL WATER RELOCATION
$47,500
DRAINAGE
1DEMO RCP STORM DRAIN$10.00$1,000
100LF
2DEMO HEADWALLS2EA$1,000.00$2,000
3CONNECT TO EXISTING RCP$400.00$800
2EA
430" CLASS III RCP150LF$90.00$13,500
524" CLASS III RCP$85.00$51,000
600LF
618" CLASS III RCP475LF$75.00$35,625
710' RECESSED CURB INLET$3,000.00$24,000
8EA
84' SQUARE MANHOLE2EA$5,000.00$10,000
9TRENCH SAFETY$2.00$2,450
1225LF
SUBTOTAL DRAINAGE
$140,375
LANDSCAPING / IRRIGATION
WEST SANDY LAKE ROAD
1LS
1
$200,000.00$200,000
404 MITIGATION 1LS
2$50,000.00$50,000
SUBTOTAL LANDSCAPING
$250,000
PROJECT SUBTOTAL
$2,969,562
20% CONTINGENCY
$593,912
PROJECT TOTAL
$3,563,500
Notes: 1) Quantity differences from City Cost Opinion attributed to the additional width of road section necessary for 4' wide on-street bike
lanes. 2) Unit cost differences from City Cost Opinion attributed to "TxDOT Factor", overall scale of project being bid, and a construction date
3-years later. (TxDOT Factor = approximately 15-20% more to construct similar projects to TxDOT standards based on recent bids.)
Page 1 of 1
George Marshall - SLR - North Coppell to Denton Tap
From: "Chris B. Seely" <cseely@tnp-online.com>
To: <gmarshall@coppelltx.gov>
Date: 11/21/2011 5:52 PM
Subject: SLR - North Coppell to Denton Tap
Attachments: PH2-OPC-4-23-04.xls
George:
Attached is a spreadsheet that covers from North Coppell to Denton Tap (both phases). I am sending it to you in
Excel so that unit prices can be adjusted since it was created in 2004. I can update the prices if you would like.
Chris
Chris Seely, P.E.
(TX)
Project Manager
TEAGUE NALL AND PERKINS, INC
.
12160 North Abrams Road Suite 508
Dallas, Texas 75243
214.461.9867 phone
214.461.9864 fax
cseely@tnp-online.com
www.tnp-online.com
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4ECA8FD5Cit...12/19/2011
OPINION OF PROBABLE CONSTRUCTION COST
SCHEMATIC DESIGN PHASE
TEAGUE NALL AND PERKINS, INC.
CONSULTING ENGINEERS
CLIENT: CITY OF COPPELL
DESCRIPTION: WEST SANDY LAKE ROAD - PHASE II
(COPPELL ROAD NORTH TO DENTON TAP ROAD)
DATE: APRIL 2004
ITEM
NO.DESCRIPTION OF ITEMSQUANTITYUNITUNIT COSTTOTAL
PAVING IMPROVEMENTS
1RIGHT-OF-WAY PREPARATION7820STA$25.00$195,500
2MOBILIZATION1LS$200,000.00$200,000
3CONCRETE REMOVAL5000SY$5.00$25,000
4HMAC REMOVAL17100SY$5.00$85,500
5UNCLASSIFIED STREET EXCAVATION50000CY$6.00$300,000
68" CEMENT STABLIZED SUBGRADE44000SY$1.85$81,400
7CEMENT STABLIZATION (42#/SY)924TON$85.00$78,540
88" REINFORCED CONCRETE PAVEMENT42400SY$27.50$1,166,000
98" ENHANCED PAVEMENT1500SY$100.00$150,000
10REMOVE 6" HMAC PAVEMENT TRANSITION1450SY$5.00$7,250
11STEPPED BLOCK RETAINING WALLS750SF$25.00$18,750
126" REINFORCED CONCRETE DRIVEWAY800SY$30.00$24,000
13PVC CONDUIT5800LF$10.00$58,000
14PAVEMENT MARKINGS AND SIGNAGE1LS$80,000.00$80,000
15BARRICADES, SIGNS & TRAFFIC CONTROL1LS$200,000.00$200,000
16EROSION CONTROL1LS$50,000.00$50,000
1710' BIKE PATH53100SF$3.50$185,850
185' SIDEWALK25650SF$3.00$76,950
19STREET LIGHT FOUNDATION60EA$2,000.00$120,000
20RESTORE PARKWAYS7820STA$20.00$156,400
21RESTORE/RECONSTRUCT EXISTING IRRIGATION1LS$30,000.00$30,000
SUBTOTAL PAVING$3,289,140
BRIDGE IMPROVEMENTS
1DEMO EXISTING BRIDGE1EA$35,000.00$35,000
2FLEXIBLE BASE280CY$50.00$14,000
318" DRILL PIERS152LF$60.00$9,120
430" DRILLED PIERS375LF$90.00$33,750
5CONCRETE ABUTMENTS105CY$550.00$57,750
6CONCRETE BENTS83CY$600.00$49,800
78" THICK BRIDGE DECK13004SF$12.00$156,048
8EXPOXY WATERPROOFING3650SF$1.00$3,650
9CONCRETE SURFACE TREATMENT12716SF$1.50$19,074
10TYPE C PRESTRESSED CONCRETE GIRDERS1581LF$70.00$110,670
11CONCRETRE RIP-RAP175CY$250.00$43,750
12STRUCTURAL STEEL - ARMOR JOINT6400LB$4.00$25,600
13SPECIAL TRAFFIC / PEDESTRIAN RAIL193LF$125.00$24,125
14SPECIAL TRAFFIC / BICYCLE RAIL386LF$140.00$54,040
15CONCRETE APPROACH SLABS144CY$250.00$36,000
16METAL BEAM GUARD FENCE400LF$25.00$10,000
17ELECTRICAL CONDUIT880LF$3.00$2,640
18LIGHT STANDARDS4EA$1,500.00$6,000
19ENHANCED PAVEMENT2175SF$5.00$10,875
SUBTOTAL BRIDGE $701,892
OPINION OF PROBABLE CONSTRUCTION COST
SCHEMATIC DESIGN PHASE
TEAGUE NALL AND PERKINS, INC.
CONSULTING ENGINEERS
CLIENT: CITY OF COPPELL
DESCRIPTION: WEST SANDY LAKE ROAD - PHASE II
(COPPELL ROAD NORTH TO DENTON TAP ROAD)
DATE: APRIL 2004
ITEM
NO.DESCRIPTION OF ITEMSQUANTITYUNITUNIT COSTTOTAL
WATER IMPROVEMENTS
1RELOCATE / ADJUST 24" WATER LINE700LF$150.00$105,000
2RELOCATE MISC. WATER (HYDRANTS, VALVES, ETC)1LS$50,000.00$50,000
SUBTOTAL WATER $155,000
SANITARY SEWER IMPROVEMENTS
18" SS LINE230LF$100.00$23,000
2ADJUST MH & MISC.1LS$10,000.00$10,000
SUBTOTAL SANITARY SEWER $33,000
UTILITY ADJUSTMENTS
1RELOCATE TXU OVERHEAD TRASMISSION POLES4EA$10,000.00$40,000
SUBTOTAL UTILITY ADJUSTMENT$40,000
STORM DRAIN IMPROVEMENTS
1DEMO RCP STORM DRAIN849LF$7.50$6,368
2DEMO HEADWALLS6EA$500.00$3,000
3CONNECT TO EXISTING RCP7EA$400.00$2,800
4CONNECT TO EXISTING 10x8 RCB1EA$1,500.00$1,500
55'X3' RCB385LF$215.00$82,775
66'X3' RCB190LF$225.00$42,750
76'X4' RCB440LF$230.00$101,200
89'X6' RCB130LF$300.00$39,000
910'X8' RCB50LF$360.00$18,000
1048" CLASS III RCP240LF$100.00$24,000
1142" CLASS III RCP110LF$95.00$10,450
1239" CLASS III RCP85LF$90.00$7,650
1336" CLASS III RCP440LF$70.00$30,800
1433" CLASS III RCP275LF$65.00$17,875
1530" CLASS III RCP185LF$60.00$11,100
1627" CLASS III RCP50LF$55.00$2,750
1724" CLASS III RCP665LF$50.00$33,250
1821" CLASS III RCP455LF$45.00$20,475
1918" CLASS III RCP900LF$40.00$36,000
2010' RECESSED CURB INLET6EA$2,500.00$15,000
2112' RECESSED CURB INLET5EA$2,750.00$13,750
2214' RECESSED CURB INLET5EA$3,000.00$15,000
2320' RECESSED CURB INLET5EA$3,500.00$17,500
244' COMBINATION INLET1EA$2,500.00$2,500
256x6 DROP INLET1EA$5,000.00$5,000
266' SQUARE MANHOLE2EA$5,000.00$10,000
275' SQUARE MANHOLE1EA$4,000.00$4,000
284' SQUARE MANHOLE7EA$3,000.00$21,000
29TRENCH SAFETY4600LF$2.00$9,200
30WINGWALL FOR MBC 9x61EA$10,000.00$10,000
SUBTOTAL DRAINAGE$614,693
OPINION OF PROBABLE CONSTRUCTION COST
SCHEMATIC DESIGN PHASE
TEAGUE NALL AND PERKINS, INC.
CONSULTING ENGINEERS
CLIENT: CITY OF COPPELL
DESCRIPTION: WEST SANDY LAKE ROAD - PHASE II
(COPPELL ROAD NORTH TO DENTON TAP ROAD)
DATE: APRIL 2004
ITEM
NO.DESCRIPTION OF ITEMSQUANTITYUNITUNIT COSTTOTAL
TRAFFIC SIGNAL IMPROVEMENT
1SIGNALIZATION FOR 2 INTERSECTIONS1LS$155,000.00$155,000
SUBTOTAL SIGNALIZATION$155,000
LANDSCAPING / IRRIGATION
1WEST SANDY LAKE ROAD1LS$500,000.00$500,000
2404 MITIGATION1LS$50,000.00$50,000
SUBTOTAL LANDSCAPING$550,000