Carter Addn 3-CS120105
DEVELOPMENT REVIEW COMMITTEE
ENGINEERING COMMENTS
ITEM:
PD-246R-SF-12, Carter Addition PH III
, a zoning change from SF-12 (Single
Family-12) to PD-246R-SF-12 (Planned Development-246 Revised-Single
Family-12), to attach a Detail Site Plan to permit 23 single-family lots and one
common area lot on 20.28 acres of property located on the south side of Carter
Drive, approximately 925 feet west of Moore Road, at the request of Toll
Brothers, being represented by Matt Alexander, Dowdey, Anderson &
Associates, Inc.
STAFF REP.: Marcie Diamond PROJECT ID# PD-11-0041
DRC DATE:
December 29, 2011 and January 5, 2012
CONTACT:
Ken Griffin, P.E., Director of Engineering/Public Works 972-304-3686
COMMENT STATUS: PRELIMINARY FINAL REVISED
AFTER P&Z
1. There will be additional comments during detailed engineering plan review.
2. Pavement will need to be 30’ back to back with mountable curbs.
DEVELOPMENT REVIEW COMMITTEE
ENGINEERING COMMENTS
ITEM:
Carter Addition PH III, Replat
, being a replat of the Carter Addition Phase III
to re-subdivide the existing 24 single-family lots and two common area lots into
23 single-family lots and one common area lot on 20.28 acres of property
located on the south side of Carter Drive, approximately 925 feet west of
Moore Road, at the request of Toll Brothers, being represented by Matt
Alexander, Dowdey, Anderson & Associates, Inc.
STAFF REP.: Marcie Diamond PROJECT ID# RP-11-
0042
DRC DATE:
December 29, 2011 and January 5, 2012
CONTACT:
Ken Griffin, P.E., Director of Engineering/Public Works 972-304-3686
COMMENT STATUS: PRELIMINARY FINAL REVISED
AFTER P&Z
1. Include the floodplain note "no fences, structures etc. allowed in the floodplain and
maintenance is responsibility of property owner etc....."