ST7301-CS 810604HOGAN & RASOR NO.2 IN COPPELL PROJECT: ESTERS ROAD-PAVING AND STORM DRAINAGE IMPROVEMENTS CONTRACTOR: AUSTIN PAVING COMPANY, DALLAS, TEXAS CONTRACT AMOUNT: $900,364.50 TIME ALLOTTED: 280 days COMPLETED TO DATE: $201,842.66 TIME USED: 55 days (19.6%) PERIOD COVERED: April 26, 1981 through May 30, 1981 The construction work performed by Austin Paving Company during the month of May included approximately 1,819 linear feet of storm sewer pipe in diameters of 42" through 18". Other work included the installation of wye fittings for pipe to pipe connections. The Contractor will continue with the storm drainage construction during the month of June and should complete all the underground work by about the middle of the month, pending favorable weather conditions. Rains and wet soil conditions during the early part of May prevented the Contractor from working. Approximately four to six days were not favorable for construction work. Construction of the 66-inch diameter R.C.P. on Line "C" HOt'AN & RASOR~ ,no. Engineers · Planners · Consultants ;~730 Repubhc Bl~mk Tow~ O~llal. Texas 75201 HOGAN & RASOR NO. 3 IN COPPELL PROJECT: ESTERS ROAD - PAVING AND STORM DRAINAGE IMPROVEMENTS CONTRACTOR: AUSTIN PAVING COMPANY, DALLAS, TEXAS CONTRACT AMOUNT: $900,364.50 TIME ALLOTTED: 280 days COMPLETED TO DATE: $244,422.71 TIME USED: 86 days (30.7%) PERIOD COVERED: May 31, 1981 through June 30, 1981 The installation of the proposed storm sewer system along Cotton Road and Esters Road (Freeport Parkway) was approximately 90% complete by the end of June, 1981. The Contractor requested the surveyors to begin the staking and layout for the paving excavation, and during the month of July, the construction work should be started on the subgrade preparation (lime stabilization). The daily construction reports furnished by the City did not indicate the Contractor lost any days of work during June due to inclement weather or wet soil conditions. 54-inch diameter R.C.P. ready for installation on LINE "D". HOGAN & I:IASOI:I, ,no. Engineers · Planners · Consultants HOGAN & RASOR NO. 4 PROJECT' IN COPPELL ESTERS ROAD - PAVING AND DRAINAGE IMPROVEMENTS CONTRACTOR: AUSTIN PAVING COMPANY, DALLAS, TEXAS CONTRACT AMOUNT: $900,364.50 TIME ALLOTTED' 280 Days COMPLETED TO DATE: $339,251.20 TIME USED: 111 days (39.6%) PERIOD COVERED: July 1, 1981 through July 25, 1981 During the month of July, Austin Paving Company began the earth excavation and lime stabilization of the subgrade. The placement of the concrete for the paving began during the latter part of the month with the south one-half (east-bound lanes) of Cotton Road and the east one-half (north-bound lanes) of Esters Road (Freeport Parkway. Other major work performed during the month of July included the excavation of the drainage channel near the north end of Esters Road (Freeport Parkway). It is anticipated that all of the concrete paving will be completed during the month of August, pending favorable weather conditions. There were no days of work lost by the Contractor during the month of July due to inclement weather or wet soil conditions, according to the daily construction reports submitted by the City. Esters Road Lime Stabilization of Subgrade Looking North from Burns Street HOGAN & RASOR, ,nc. Engineers · Planners · Consultants