George Marshall - FW: Belt Line
From: <brad.moss@kimley-horn.com>
To: <gmarshall@coppelltx.gov>
Date: 9/27/2011 6:56 PM
Subject: FW: Belt Line
CC: <ryan.delmotte@kimley-horn.com>, <aduggan@studiooutside.us>
Attachments:C-COPPELL INTERSECTIONIMPROVEPLANC0.04 BELT LINE ROAD AT
SAINTSBURY STREET (1.pdf
George-
Any answer back yet on the crosswalk for Cypress Waters? We are sending our plans out to bid on Thursday and we
would like to have the Beltline improvements incorporated into the bid set of plans. Attached is a PDF exhibit that
shows the 15’ crosswalk across Beltline. The ped poles are not finalized b/c we want to make sure you are okay with
these ramp locations and crosswalk before we move those around. The ramps and the 12’ crosswalk meet the City
of Coppell details. The landscape architect is also reviewing the ramp locations and style and may propose
something different as this is the main entrance in to Cypress Waters and they may want to add some of their style
to it as they did throughout the rest of the Cypress Waters development. I will let you know what they propose. The
crosswalk crossing Saintsbury is within the City of Dallas so we left that width the same.
Besides the locations shown, the outstanding question I had for you was the need for stamped concrete now vs.
later,
Please let me know your thoughts tomorrow morning if possible.
Thanks.
®
Bradley Moss, PE , LEED AP
(TX, OK, NC)
12700 Park Central Drive
Dallas, Texas 75251
Ph: 972-770-1300 Fax: 972-239-3820
brad.moss@kimley-horn.com
From: Delmotte, Ryan
Sent: Tuesday, September 27, 2011 6:10 PM
To: Moss, Brad
Subject: Belt Line
Brad,
Once we get the final ramp locations we can update the ped button locations. It looks like some of them are showing
up within the limits of the sidewalk.
Ryan M. Delmotte, EIT | Kimley-Horn and Associates, Inc. | 2201 West Royal Lane Suite 275 Irving, TX 75063 |
| |
214.420.5624 direct214.420.5600 main214.420.5680 fax | |
ryan.delmotte@kimley-horn.comwww.kimley-horn.com
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4E821C77City_...1/26/2012