October 24, 2002
Mr. Mark Gray
Rone Engineers
8908 Ambassador Row
Dallas, Texas 75247
RE: Ruby Road
ST 01 -02
Construction Materials Testing
Dear Mr. Gray:
The City of Coppell intends to construct the Ruby Road project. The project consists of
the reconstruction of 2700 linear feet of an existing two -lane asphalt road to a two -lane
undivided concrete roadway, 2220 linear feet of storm drain, 2900 linear feet of water line,
and 750 linear feet of sanitary sewer pipe. It is anticipated that construction will begin in
December 2002. We are providing an estimate of the type and number of construction
materials tests required for the project based on the construction plans and the City's
standards. The contractor is responsible for payment of materials testing done before
8:00 a.m. and after 5:00 p.m. Please submit a proposal for the construction materials
testing.
Your consideration of this matter is appreciated and should you have any questions or
need any additional information, please contact me at 972 - 304 -3679.
Sincerely,
c
Suz Taylor
C.I.P. ordinator
Attachments
255 PARKWAY * P.O. BOX 478 * COPPELL TX 75019 * TEL 972/462 0022 * FAX 972/304 3673
RUBY ROAD PROJECT (STO1 -02)
CONSTRUCTION MATERIALS TESTING ESTIMATE
Site Preparation
Approximately 4515 C.Y. of fill material will be placed. (Assumed 1 FDT per 8" lift for
each 300 feet.)
1. Nuclear Density Test ........................... 25 /each
2. Standard Proctor Test ........................... 2 /each
3. Atterberg -limit Test ............................. 2 /each
Mechanical Lime Stabilization
Approximately 10,905 S.Y. (2700 L.F.) of subgrade will be mechanically lime stabilized.
(Assumed 1 FDT and Gradation for each 300 L.F.)
1. Nuclear Density Test ............................ 9 /each
2. Standard Proctor Test ........................... 3 /each
3. Atterberg -limit Test ............................. 3 /each
4. Gradation .......... ............................... 9 /each
Concrete Testing
A total of 2000 C.Y. will be placed. (Assumed 1 set of 4 cylinders each 150 C.Y. plus
another 25% for hand - pours)
1. Concrete Compression Tests (Paving) ............ 65 cylinders
2. Concrete Compression Tests (4 Manholes) .......... 12 cylinders
3. Concrete Compression Tests (9 Inlets) ............36 cylinders
4. Concrete Compression Tests (4 Headwalls) .......... 8 cylinders
Utilities
Storm Sewer- (A total of 2221 LT
FDT per each 8" lift.)
Water Line - (A total of 2900 L.F.
FDT per each 8" lift.)
Sewer Line — (A total of 750 L.F.
lift.)
of 12 "- 48" and assumed average depth of 4' and 1
of 6" —12" and assume an average depth of 4' and 1
of 8" and depths of 5' to 12' and 1 FDT per each 8"
1. Nuclear Density Test ....... .......................13 /each
2. Standard Proctor Test .............................. 2 /each
3. Atterberg -limit Test ........... .....................2 /each
HMAC
Asphalt Extraction Type "D" ....................... 1 /each