Loading...
ST8503-CS 870804GINN. IN{i. (]ONSI'LTIN¢; EN{;INEERS August 4, 1987 / Ed Bell ConStruction Company Post Offi~ Box 20777 Dallas,~lroxas 75220-0777 Attention: Tom Bethune, Jr., P.E. Re: Bethel School Road Coppell, Texas Gentlemen: Enclosed for your files are two (2) sets of executed contract documents for the above referenced project. You are hereby notified to commence work on the Bethel School Road Improvements on or before September 1, 1987, and shall fully complete all of the work within 300 consecutive Calendar days thereafter. Your completion date is June 26, 1988. The contract documents provide for an assessment in the sum of $250.00 per calendar day as liquidated damages for each consecutive calendar day after the above established contract completion date that the work remains incomplete. Dated this 4th day of August, 1987. By: H. Wayne Ginn, P.E. ACCEPTANCE OF NOTICE TO PROCEED Receipt of the foregoing Notice to Proceed order is hereby acknowledged by , this day of , 1987. By: Title: Please sign and return one copy for our files. Should you have any questions, please contact us. -2- A preconstruction conference will be held Monday, August 10, 1987, 10:00 a.m. at the Council Chambers, City of Coppell City Hall, 255 Parkway Blvd. Please have all interested parties attend. Sincerely, Gabe Favre GF/jc cc: Mayor and Council Members Alan Ratliff, City Mgr. Steve Goram, Dir. Pub. Wks. H. Wayne Ginn, P.E. Ronnie Bates, Ginn, Inc. EB802257