Red Hawk-CS120314
Page 1 of 2
Rhonda Adloo - Re: FW: minor replat/ Red Hawk
From: Michael Garza
To:Terry Holmes
Date: 3/14/2012 4:22 PM
Subject: Re: FW: minor replat/ Red Hawk
CC:Lynn Kadleck; Rhonda Adloo
Terry,
The meters on lot 28 are supposed to go in the water easement on the east side of that wall near the proposed
driveway. Originally you had them located on Blackburn Dr. DRC is just a preliminary review, we do not
approve plans that go through DRC. We only approve plans that come through the detailed plan review
process. We will not approve the location of the services for Lot 27 as shown, they will need to be on the
Denton Tap side for that commercial lot. You will either need to tap into the water main under Denton Tap or
tap the water main to the south. When you submit plans for these commercial lots we will assess the impact
fees. Changes or additions like these should not occur in the field and work should not occur on lots that do not
have plan approval.
Also since you do not have any property corners staked we can not verify locations of pavement, inlets, ROW,
etc. We will not allow any early releases until we can verify these items. Also you need to have that large
stockpile of material along with the trees that have been piled up and sitting there for months removed before
we allow an early release. The bag wall around the headwall will also need to be completed before we allow any
building permits to be released.
Last note: you need inlet protection on the all of the inlets. We will make you clean out the creek prior to final
acceptance.
If you have any questions please contact me at your convenience.
thanks,
Mike
Michael Garza
Engineering Dept.
City of Coppell
Office: 972-304-7019
Fax: 972-304-3570
Please consider the environment before printing this e-mail
>>> On 3/14/2012 at 12:26 PM, in message <004101cd0207$a6e3dc70$f4ab9550$@theholmesbuilders.com>,
"Terry Holmes" <terry@theholmesbuilders.com> wrote:
Mike,
At lot 27/A we added a 1” and a 1 ½” service (never thinking that I needed to check with the city), so they
would not destroy as much of the HOA’s landscaping when that lot is built upon. We would have 2- 1”
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4F60C5D4City_...3/14/2012
Page 2 of 2
meters and pay for the fees when that lot is obtains a building permit. We would like to set the loop and
the meter can now. Is that okay? Larry wanted me to get with you in this. I have attached a copy of the
locations of the services along with the proposed site plan and elevation that I sent to Gary Sieb, earlier
this week.
At lot 28/A the 1” and 1 ½”services were moved off of Bethel road, and onto Blackburn. They are still in
the ROW. I think this was changed was recommended by the city (for safety of the meter reader), during
the DRC for lot 28/A. These too would both have 1” meters. I wanted to make sure that was okay with
you. All the change will be reflected on our as built plans.
Working Together,
Terry Holmes
The Holmes Builders
225 E. Hwy 121, St 120
Coppell, Texas 75019
o. 214.488.5200 x205
c. 469.446.1165
f. 214.488.5255
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4F60C5D4City_...3/14/2012